Generally speaking, the installation procedures of industrial steel building include installation of steel columns, installation of inter-column supports, temporary installation of steel crane beams, roof beams, roof supports, steel crane beams, etc., correction, fixation, and structural installation of maintenance.
What is the specific process of industrial steel building construction?
How to regularly maintain industrial steel building?
How to consider the cost of industrial steel building construction?
1. Lifting the main structure of industrial steel buildings: connecting steel carriers on the ground, erecting steel columns, lifting steel carriers, connecting secondary structures, correcting the deviation of the main structure, installing crane carriers (optional), lifting intermediate layers (optional), and coating with fire resistant paint pack.
Main control quality: The deviation of the main structure should meet the specifications and design requirements and the initial and final application of high-strength screws should meet the requirements.
2. Installation of secondary structure: roofing posts, roof wall supports, flange supports, etc.
3. Laying of roof plate and insulation layer: first lay insulation layer, then assemble roof plate (in some projects a position of steel fabric is also placed under the insulation layer to prevent a fall of the insulation layer, this mainly depends on insulation layer level)
Main quality control: The roof is mainly waterproof, therefore the plate should be covered with the plate, the nail position, the glue coating should be full or not, the glue should be wiped clean and the coating on the surface of the plate should not be damaged to rust etc. to avoid.
industrial steel building wall maintenance and installation: mainly the installation of wall insulation and wall panels.
The main quality control of industrial steel building: the wall is mainly an aesthetic problem, and a window area is waterproof. There is also the problem of installation deviation. For example, the bottom should be flat, the entire plane should be flat, the flatness deviation between the board and the board should meet the requirements, and so on.
The detailed structure of the industrial steel building: mainly the installation of some trims, such as the wrap angle between the roof and the wall, the wrap angle at the corner of the wall, the flooding board between the wall panel and the brick wall, the door and window trim, etc.
The price of industrial steel building can only be compared with certain basic conditions, such as whether it is imported or domestic color panels, its thickness, coating; insulation material and thickness; whether there is a skylight; workshop bays and spans; whether there are cranes, crane tonnage, Many factors such as the level of the work system are related, and the impact of the price difference in other regions and the qualification level of the construction unit cannot be ignored.
The industrial steel building has achieved an irreplaceable position in industrial production. Qingdao Xinguangzheng Steel Structure Co., Ltd. is committed to providing different kinds industrial steel buildings of high quality for all customers from all over the world.
Steel building accessories are constructed of steel materials. It is one of the main types of building structures. The structure consists mainly of steel bearings, steel columns, steel joints and other components made of profile steel and steel plates and uses rust removal and rust protection methods such as silylation, pure manganese phosphation, water washing and drying, galvanizing and so on.
Prefabricate and assemble steel building accessories on the steel platform according to the installation sequence and process requirements to ensure the welding quality.
The spacing between the splicing joint of flange plate and web plate of section steel shall be greater than 200mm. The splicing length of flange plate shall not be less than 2 times of plate width; The web splicing width shall not be less than 300 mm and the length shall not be less than 600 mm.
In order to facilitate welding and ensure welding quality, the stiffener plates, connecting plates, base plates and cantilever beams (beams) on columns and beams shall be assembled and welded on the ground steel platform according to the dimensions of the construction drawing.
The Steel building accessories prefabricated on the steel platform shall not only be fabricated and assembled according to the construction drawings and specifications, but also consider the process of on-site installation and the change of installation size.
Some Steel building accessories users do not know that steel structures still need to be maintained and maintained. As a result, there is serious corrosion that users often can't find out, which makes steel products appear many unsafe hidden dangers, reduces the safety of Steel building accessories in use, and even affects normal use functions. It is recommended that the design unit not only put forward the painting requirements of the steel structure in the painting design description of the steel structure, but also put forward the maintenance and maintenance requirements of the Steel building accessories according to its use.
There are many ways to prevent steel building accessories from rusting, and the following are usually used:
The steel structure is made of alloy steel that is not easy to rust
Chemical oxide layer protection method
Using metal coating protection method
Non-metallic coating protection law
In the later maintenance and maintenance process, non-metallic coating protection method is especially commonly used. The surface of the component is protected by paint and plastic, so that it does not contact the surrounding corrosive medium, so as to achieve the purpose of anti-corrosion. This method has good effect, low price, and has a wide range of paint varieties, a wide range of options, and strong applicability. It is not limited by the shape and size of the component. It can form a film with any shape on the surface of the component. The adhesion is firm. It can also follow the temperature change. The components are telescopic and easy to use. It is also possible to give the component a beautiful color.
Great products begin with the best engineering staff, and Qingdao Xinguangzheng Steel Structure Co., Ltd. is ready to assist you with your technical requirements for steel building accessories.
Due to the increase in steel production in the world, many new factories have begun to introduce industrial steel buildings which can be divided into factories for light and heavy steel structures. Steel structures are industrial and civil engineering installations made of steel.
What are the reasons why people opt for industrial steel building?
What are the advantages for people who opt for industrial steel building?
What is the order of installation of industrial steel buildings?
Comfort
The industrial steel building uses a highly efficient and energy-saving system, has a respiratory function and can regulate the dry humidity of the inner air; The roof has a ventilation function that can form a flowing airspace over the house to ensure the ventilation and thermal drainage requirements within the roof.
Quickly.
The industrial steel building is completely dry and is not affected by the environmental season. With a building of about 300 square meters, only five workers and 30 working days can complete the entire process from foundation to decoration.
Environment
The material of the industrial steel buildings can be recycled to 100% which is really green and free of pollutants.
Save energy
All industrial steel buildings use high-efficiency energy-saving walls that have good heat storage, thermal insulation and sound insulation and can achieve 50% energy-saving standards.
1 industrial steel building has a wide range of applications: it can be used in factories, warehouses, office buildings, stadiums, hangars, etc. to be used. It is suitable not only for single-storey and wide-stretched buildings, but also for the construction of multi-storey or high-rise buildings.
2 The construction of the industrial steel building is simple and the construction time is short: all the components are pre-fabricated in the factory, the construction site only needs to be simply assembled, which greatly shortens the construction time. For a 6000-square meter building, the basic installation can be completed in just 40 days.
3 The industrial steel building is durable and easy to repair: the steel building constructed by universal computers maintains rough weather conditions and requires simple maintenance.
4 industrial steel building is beautiful and practical: steel construction has simple and smooth lines with a modern sense. The coloured wall panels are available in a variety of colours, and the walls can also be made of other materials, making them more flexible.
5 The cost of industrial steelmaking is reasonable: the steel structure has a low weight, reduces the cost of the foundation and is fast in construction. It can be completed and put into service as soon as possible. The overall economic benefits are much better than those of concrete construction.
Installation procedures for industrial steel buildings:
Steel column installation → installation of support between columns → temporary installation of steel crane beams → roof beams, roof supports → correction and fixation of steel crane beams → maintenance of structural installation.
Qingdao Xinguangzheng Steel Structure Co., Ltd. strives to provide top-quality industrial steel buildings with reasonable prices, efficient production time, and the most professional customer service.
1. The positioning axis and supporting surface elevation of the foundation are out of tolerance:
The positioning axis of the foundation and the elevation of the supporting steel cylinder exceed the allowable deviation.
The reasons are as follows:
There are errors and deviations in foundation survey control network, foundation survey setting out and elevation finding.
The foundation formwork is not firmly set up, the pouring concrete blanking is too high, and the concrete is vibrated and impacted, which makes the formwork displacement and causes the datum line deviation.
Or the use of steel ruler, theodolite, level without calibration, there are errors.
Or construction wrong drawings, axis wrong, without strict inspection.
Or if the foundation bearing surface is not plastered and leveled twice, the concrete will shrink and sink.
Or the embedded steel plate (or support) is not fixed.
Because the foundation positioning axis and bearing surface are out of tolerance, the column installation axis and bearing elevation will be out of tolerance, which will affect the quality of the whole structural steel construction installation project.
Avoiding measures:
(1) The accuracy of basic survey control network, instruments and measuring tools used for basic survey setting out and leveling shall be accurate. Before use, they must be checked or verified by the measurement department. If problems are found, they shall be adjusted in time to prevent errors or accumulated errors, resulting in axis and elevation exceeding the allowable deviation.
(2) The foundation formwork for steel structure construction must be firmly supported with sufficient strength and rigidity. When pouring concrete, cutting and vibrating, it is necessary to prevent from striking the formwork and causing displacement. In the process of concrete pouring, the positioning axis and elevation shall be checked regularly with measuring tools or suspension lines. If any deviation is found, the pouring and vibration shall be stopped, and the work shall be carried out after reinforcement and adjustment. Before the final setting of concrete, the surface of foundation concrete shall be plastered and leveled twice. For the embedded steel plate or bearing, the elevation and levelness shall be aligned twice, and the concrete at the bottom shall be dense. The steel plate or support of foundation support column shall be provided with necessary fixing devices to ensure correct position and elevation.
(3) When the elevation and levelness of the steel plate or support on the vertical and horizontal axis of the foundation and column bearing surface are out of tolerance, measures shall be taken according to the degree of deviation. When the out of tolerance is not serious, it can be solved by shifting the column base, reaming and packing the base plate. If the deviation is serious and cannot be adjusted, it should be studied with relevant departments to work out a feasible correction scheme before treatment.
2. Foundation anchor bolt thread damage:
The foundation anchor bolt thread is damaged, and the nut cannot be screwed and tightened during the column installation.
The causes of bolt thread damage are as follows:
Anchor bolts are impacted or improperly kept during transportation, loading and unpacking, resulting in serious thread corrosion.
Or the bolts were not protected after burying and were damaged by outside.
Or the bolt is used as electric welding zero line on site, and the thread is damaged due to arc burn.
Or the bolt is used as the binding point of the pulling force of the traction rope.
Due to the damage of bolt thread, it is impossible to screw in nuts to fasten steel columns and other components, which affects the transmission and stability of structural force.
Avoiding measures:
(1) When the anchor bolts are transported, packed and unpacked, the thread protection shall be strengthened. After being smeared with industrial vaseline oil, they shall be wrapped and bound with plastic film to prevent thread damage and corrosion. And should be stored separately, should not be mixed with other parts and components, so as to avoid mutual impact damage thread.
(2) After the anchor bolt is embedded, it shall not be used as the fulcrum of bending processing, the neutral line of electric welding machine, or the binding point of traction force. When lifting components, proper operation shall be carried out to prevent the thread from being damaged by horizontal lateral impact force.
(3) The screw thread of the bolt has been damaged, and the following treatment methods can be adopted: when the damaged length of the screw thread does not exceed its effective length, the steel file can be used to trim the screw thread, so as to smoothly screw in the nut. When the length of thread damage of local foot bolt exceeds the specified effective length, the length of original thread section can be cut by gas cutting; Then, with the same material and specification as the original bolt, one end of the bolt is processed into thread, and the butt end section is made into 30º-- 45º. After butt welding with the lower end of the groove, the corresponding diameter specification and length of the steel casing sleeve into the joint, welding reinforcement. After casing reinforcement for steel work in construction, the diameter of the bolt will be larger than that of the base plate, which can be solved by appropriately enlarging the diameter of the base plate.
3. The setting of mortar base plate of column base does not meet the requirements:
The mortar base plate of column base is set randomly, and the elevation, levelness and position do not meet the design and specification requirements.
The reasons are as follows:
The surface of the foundation is not treated and leveled, so that the base plate can not bear the force smoothly, and the surface is uneven and uneven;
The base plate is not reasonably arranged according to the stress requirements, so that the base, base plate and foundation can not bear uniform pressure, so that the settlement of base slurry is uneven, and the elevation and levelness can not meet the requirements.
If the setting of open base plate does not meet the requirements, it can not transfer the load evenly, which will reduce the mechanical performance of the column and affect the stability of the superstructure.
Avoiding measures:
(1) In order to make the base plate group transmit the force to the foundation smoothly, the base plate should be closely combined with the base slurry on the foundation surface. The uneven foundation surface shall be chiseled and leveled.
(2) The location and distribution of the base plate should be correct. Generally, according to the stress area of the steel column base plate, the base plate, the base plate and the foundation should be arranged in the center of the steel plate and the stress concentration position on both sides or near the two sides of the anchor bolt, so that the base plate, the base plate and the foundation can fully bear the pressure load, and bear the force uniformly together to avoid partial bias Concentrated stress or deformation of the base plate occurs when the anchor bolts are tightened.
(3) The area of the base plate directly bearing the load should meet the needs of the stress, which should be determined by calculation, and the area should not be too large or too small. Too large will cause waste, too small will cause local concentrated overload of foundation and affect the overall and uniform stress of foundation. The thickness of the base plate is generally within the range of 4 ~ 25 mm, each group is no more than 3 pieces. The base plate has a 10 ~ 12 mm thick steel plate, the length of the base plate is 100 ~ 300 mm, and the width is 50 ~ 120 mm. When setting the mortar, use non shrinkage cement mortar with strength not lower than 30MPa. As the steel column is mainly installed with cushion plate to adjust the elevation and levelness, the elevation and levelness shall be found when grouting, and the allowable deviation shall comply with the specification, and the supervision shall be strengthened. Before the base plate is grouted, the rust, oil stain and burr on the surface of the base plate shall be cleaned, so that the base plate can be firmly combined with the concrete when grouted and grouted; The length of the base plate group exposed to the outside of the base plate edge is about 10 ~ 20 mm.
4. Before the installation of steel column, the foundation is directly installed without inspection:
Before the installation of steel column, the axis and elevation of the foundation, the position and elevation of the anchor bolt and the concrete quality of the foundation are not checked in advance, so the installation is carried out directly. In this way, there may be out of tolerance without repair, which will cause structural installation difficulties, increase the steel column installation stress and affect the installation accuracy, and even cause quality hazards.
Avoiding measures:
Before the installation of steel column, the positioning control line, foundation axis, elevation, anchor bolt position, elevation and concrete quality of foundation shall be pre checked. If the deviation is found, measures shall be taken to correct and adjust to the allowable deviation range of the specification. For elevation inspection, the measured data shall be compared with the pre inspection data of steel column size and elevation, and the error of the two shall be eliminated when the support base slurry pad or anchor bolt nut is adjusted. The allowable deviation of foundation support surface, anchor bolt position and base slurry pad shall meet the requirements of the specification. The quality of foundation concrete shall be dealt with in accordance with relevant regulations.
5. Don't check the dimension of steel members, deal with deformation and quality defects before installation
Before the installation of the structure, the external dimensions of the steel members are not checked, and the deformation and quality defects of the members are handled.
Although the steel components have passed the quality inspection before they are processed in the factory, they may fail to be inspected, or new deformation and damage may occur in the transportation and stacking of the components. If the review is not carried out before the installation, these problems can not be dealt with in time before the installation, which will affect the installation quality of the steel structure and cause installation difficulties or permanent quality defects.
Avoiding measures:
Before the installation of steel members, the steel members shall be carefully checked in advance:
It includes checking the model and quantity of the component, the overall dimension of the component, the relevant dimensions between the supporting surfaces and the installation holes, and marking the datum line of the axis of the component. Check whether the component is deformed, and correct and repair the deformation error if there is any.
Whether the connecting plate, splint and other accessories of the component are complete and whether the position and size are accurate. Inspect whether the surface quality of the welding area of the component and the friction surface of the high-strength bolt connection meet the requirements and whether it is polluted.
Whether the member nodes are complete and whether the center of gravity of main components is marked.
Whether the surface of the component is polluted, whether the paint falls off, etc.
Pre inspection records of components shall be made; For the components with deformation and defects exceeding the allowable deviation, they shall be corrected and repaired on the ground before installation, and can be installed after they are qualified.
6. The perpendicularity of steel column installation is out of tolerance:
The verticality deviation of steel column exceeds the allowable value in design or code
When the steel column is manufactured, the deformation control measures are not taken or the bending deformation is not straightened.
Or the length of the column is large, the rigidity is poor, and the elastic or plastic deformation occurs under the action of external force.
Or due to the unreasonable hoisting technology and procedure, the roof panel is bent and deformed under the action of temperature, wind and external force.
Or there is deviation in the span size of the roof truss, the external force is used to force the connection during the installation, resulting in the over deviation of the verticality of the steel column.
This will lead to the deflection of the steel column and affect the bearing capacity and stability.
Avoiding measures:
(1) Anti deformation measures shall be taken for assembly and welding of steel column, and the deformation during fabrication shall be corrected in time. When transporting and stacking steel columns, the supporting points should be appropriate to prevent bending deformation under the action of self weight. The out of plane stiffness of long column is poor, so the lifting point should be selected at 2 / 3 of the total length of the column to prevent deformation. If the span size of steel roof truss exceeds the deviation, it should be corrected before installation to prevent forced connection and bending deformation of column body.
(2) When the steel column is hoisted to the foundation plane in place, the vertical and horizontal axis above the column base plate should be aligned with the foundation line, so as to prevent the deviation of span size, which will lead to the horizontal tension or thrust when the column head is installed and connected with the roof truss, so as to make the column body bending and deformation, and carry out appropriate control.
(3) When the roof slab is hoisted after the connection and installation of the steel column and the tail-stock, it should be carried out symmetrically and synchronously from the edge of the two slopes in the center of the top chord to the middle, so as to prevent the bending deformation of the steel column caused by the lateral concentrated pressure generated by the one slope. Without the permission of the design, the steel column and other connected components shall not be used for horizontal dragging or vertical hoisting of heavy components and equipment, and the column bending deformation or damage to the connecting structure shall be prevented.
(4) If the bending steel column is elastic deformation, it can be restored to its original state after the external pressure is removed; If it is plastic deformation, it can be corrected by adding temporary support above or at the top of the bending part of the steel column before correction, so as to reduce the load-bearing gravity, and then fixing one side reaction frame at the bending part, and using jack for correction. If the rigidity of the steel column is large, it can be corrected by heating the bending convex surface with oxyacetylene flame, and then applying jacking force.
7. Steel column installation height is out of tolerance:
Height dimension or relative position of steel column after installation (±) The elevation dimension is out of tolerance, which makes the difference between the total height of each column and the height deviation of the bracket.
The reasons are as follows
Foundation elevation is incorrect or deviation occurs.
The length and dimension of steel column during the production stage are out of tolerance.
Or when the foundation elevation is adjusted and treated during installation, it is not combined with the actual length (height) of steel column, which will cause the positive or negative difference of the height dimension or elevation dimension of the steel column after installation.
Because of the over tolerance, it is difficult to install and adjust the components connected with it, which makes it difficult to correct and takes time.
Avoiding measures:
(1) During the foundation construction, the elevation size should be strictly controlled to ensure the accuracy of elevation. The elevation dimension of the upper surface of the foundation shall be adjusted according to the actual length of the steel column or the elevation dimension of the bracket supporting surface, so as to make it consistent with the height and elevation dimension of the steel column after installation.
(2) During the manufacturing process of steel column, the length and size (including the total length and the length of each position specified in the design, the length and size within the allowable positive and negative deviation range, and the positive excess value not allowed) and the correct size of the total length and bracket of the steel column without contact point shall be strictly controlled. The latter can be adopted to weld the column body first, and the column base plate and column head plate shall not be welded temporarily, In case of out of tolerance, adjust before welding the base plate or upper column head plate of the column, and finally weld the base plate and column head plate of the column.
Pictures for Prefab Metal Workshop Steel Structure Construction Workshop House in Costa Rica
Drawings & Quotation
1) Customized design is welcomed.
2) We have an excellent design team. According to the requirements of different projects and clients,we will supply different designs and steel products.In order to give you an exactly quotation and drawings, please let us know the following informations. We will quote for you promptly.
Basic design requirements of steel structure warehouse
Basic Design Requirements | ||
1.Project location | 5.Length (side wall,m) | 9.Window quantity, size |
2.Snow load | 6.Width (end wall, m) | 10.Door quantity, size |
3.Wind load | 7.Wall Height (eave, m) | 11.Brickwall needed or not. If yes, 1.2m high or 1.5m high |
4.Seismic magnitude | 8.Middle column allowed or not | 12.Crane needed or not |
13.Thermal insulation. If yes, EPS, fiberglass wool, rockwool, PU sandwich panels will be suggested; If not, the metal steel sheets will be ok. The cost of the latter will be much lower than that of the former. |
Engineering Design Software:
AutoCAD, PKPM, MTS, 3D3S, Tarch,Tekla Structures(Xsteel)V12.0.etc.
Cheap prefab structural steel warehouse prefabricated outdoor storage shed building design price steel structure warehouse
Residential steel building is a residential system composed of an envelope structure and a steel supporting structure. It is a new type of energy-saving and land-saving residential system. Its steel structure residence abandoned solid clay bricks and effectively used land resources. Compared with traditional houses, steel structure houses have advantages in terms of use function, design, construction and comprehensive economy.
What are the reasons why people choose Residential steel building?
What should the choice of Residential steel building structural system look like?
What is the framework system used by Residential steel building?
1. Residential steel building energy saving and environmental protection
The main body of the Residential steel building is steel components, and the wall material is thermal insulation mortar, which not only meets the requirements for energy saving, but also can be recycled. It is a green and environmentally friendly recycling building that meets the requirements of sustainable development. The thermal resistance can reach a brick wall thickness of about 1m. At present, the global population is large and energy consumption is large, and the promotion and application of steel structure housing is the final choice.
2. Residential steel building's pipe network line layout is convenient
In residential buildings, there are many lines of professional plumbing and electricity pipe network, which will reduce the effective use area in traditional buildings. In residential steel building, there are many holes or holes in beams and columns, which is easy to form a cavity for wiring layout. Moreover, the beam can be artificially made into a honeycomb shape, which is convenient for line layout, which not only saves the net height of the building, but also increases the use area.
According to engineering practice, the commonly used Residential steel building structure system can be selected with reference to the following scope:
The 4th to 6th floors are the steel frame system, the steel frame-support system, and the steel frame-shear wall system; the 7th to 12th floors are the steel frame-concrete core tube (shear wall) system.
The section form of steel components should be hot-rolled H-section steel, high-frequency welded H-section steel and steel tube concrete.
Light steel frame system
The light steel frame system is a load-bearing frame composed of hot-rolled H-shaped steel (or I-beam), high-frequency welded H-shaped and cold-formed square pipes, and a steel structure residence with composite curtain walls or infill walls as the enclosure structure system.
The wall panels in the picture collection are made in the factory with fly ash as the filler, sulfoaluminate as the cement, polystyrene foam (EPS) as the core material, and glass fiber mesh as the reinforcement material. A lightweight board. Special adhesive is used to bond the plate and the light steel frame, and between the plate and the plate. To prevent thermal bridges using double-layer plates.
Qingdao Xinguangzheng Steel Structure Co., Ltd., as a leading company in China's residential steel building, has committed to providing the most suitable residential steel building at a reasonable price, and whatever it takes to satisfy the customer's needs.
Commercial steel building, the preferred steel and metal building in construction, has quickly become the first choice for residential and commercial building safety. Here we are going to talk more about the Commercial steel building !
What are the advantages of Commercial steel building?
Why do more and more people choose Commercial steel building?
What are the advantages of Commercial steel building?
In this field of commercial construction, Commercial steel building has greatly exceeded the normal construction capabilities of its competitors.
Because Commercial steel building has a quality guarantee of up to 40 years, the steel structure of the building is durable.
For the daily maintenance of wall panels, roofs and metal buildings, steel structure owners may pay a huge price for this, because steel structure houses are more resistant to wear and tear than other materials every day.
Commercial steel building is safe in extreme weather. When your country/region is under extreme climatic conditions, such as earthquakes, tornadoes, ice storms, or just a strong thunderstorm, this Commercial steel building is proven to be more resistant than others because it is made of steel .
Because of this, government agencies and municipalities always choose Commercial steel building to protect their most important property from severe weather.
Because of this, more and more residential customers choose to use steel to build their houses for maximum protection.
With a steel structure, you can have many advantages, such as economy, beauty and reliability.
In addition to these eye-catching features, Commercial steel building also has great flexibility for customers who want to configure ideal buildings to meet their precise requirements and satisfy their aesthetics.
Compared with other buildings, customized Commercial steel buildings and residences provide users with more versatility, and metal buildings are also a very economical choice for new buildings.
The steel structure of Commercial steel building has a series of advantages, such as high strength, light weight, good seismic performance, high degree of industrialization, fast construction speed, small floor area and so on. Steel has good mechanical processing performance, which is most easy to realize modular, standardized, industrialized, assembled and mechanized production of buildings, realize no fire, no water, no dust and no garbage on the construction site, have good recycling of steel, and most easy to realize the concept of full-life green building. Due to the strong plasticity of steel structure, it can be widely used in civil buildings, public buildings and commercial buildings. Such fields as industrial plants, low rise, multi-storey and super high-rise buildings, civil residences, large public buildings, terminal buildings, thermal power plants and boiler steel frames, highway and railway bridges and offshore oil platforms.
Qingdao Xinguangzheng Steel Structure Co., Ltd. is a Commercial steel building manufacturer established for more than several years. Please consult our company for details through https://www.steelstructureonline.com/! Customer requirements are our pursuit.
The full name of MDC is"MONDU DA CASA (home world)", which is constructed by Qingdao Xinguang Zheng Steel Structure Co., Ltd. This is a comprehensive shopping center centering on the theme of "happy home". This theme is the same as the enterprise mission of "benefiting the society, achieving employees and making customers happier". In addition to "home world", she has another interpretation of "modern decoration Center".
MDC is located in KIKUXI section of Luanda expressway, surrounded by Angola national stadium, high-end residential villa area, Brazil nursery garden, and Luanda commercial pedestrian street under planning, with superior geographical environment and convenient transportation.
"MDC home world" shopping center covers an area of about 30000 square meters. Relying on the global procurement network, it has gathered kipor generator 4S shop, furniture store, building materials store, home furnishing store and home appliance store. The categories include building materials pipe fittings, wood, floor tiles, paint and coating, decorative lamps, kitchen and bathroom equipment, hardware tools, electrical and electrical materials, gardening supplies, cloth furniture, home appliances, etc., and also auxiliary It is one of the most comprehensive "one-stop purchasing" centers for home furnishings in Luanda with public service facilities such as business office, catering, leisure and entertainment, bank, etc.