Generally speaking, the installation procedures of industrial steel building include installation of steel columns, installation of inter-column supports, temporary installation of steel crane beams, roof beams, roof supports, steel crane beams, etc., correction, fixation, and structural installation of maintenance.
What is the specific process of industrial steel building construction?
How to regularly maintain industrial steel building?
How to consider the cost of industrial steel building construction?
1. Lifting the main structure of industrial steel buildings: connecting steel carriers on the ground, erecting steel columns, lifting steel carriers, connecting secondary structures, correcting the deviation of the main structure, installing crane carriers (optional), lifting intermediate layers (optional), and coating with fire resistant paint pack.
Main control quality: The deviation of the main structure should meet the specifications and design requirements and the initial and final application of high-strength screws should meet the requirements.
2. Installation of secondary structure: roofing posts, roof wall supports, flange supports, etc.
3. Laying of roof plate and insulation layer: first lay insulation layer, then assemble roof plate (in some projects a position of steel fabric is also placed under the insulation layer to prevent a fall of the insulation layer, this mainly depends on insulation layer level)
Main quality control: The roof is mainly waterproof, therefore the plate should be covered with the plate, the nail position, the glue coating should be full or not, the glue should be wiped clean and the coating on the surface of the plate should not be damaged to rust etc. to avoid.
industrial steel building wall maintenance and installation: mainly the installation of wall insulation and wall panels.
The main quality control of industrial steel building: the wall is mainly an aesthetic problem, and a window area is waterproof. There is also the problem of installation deviation. For example, the bottom should be flat, the entire plane should be flat, the flatness deviation between the board and the board should meet the requirements, and so on.
The detailed structure of the industrial steel building: mainly the installation of some trims, such as the wrap angle between the roof and the wall, the wrap angle at the corner of the wall, the flooding board between the wall panel and the brick wall, the door and window trim, etc.
The price of industrial steel building can only be compared with certain basic conditions, such as whether it is imported or domestic color panels, its thickness, coating; insulation material and thickness; whether there is a skylight; workshop bays and spans; whether there are cranes, crane tonnage, Many factors such as the level of the work system are related, and the impact of the price difference in other regions and the qualification level of the construction unit cannot be ignored.
The industrial steel building has achieved an irreplaceable position in industrial production. Qingdao Xinguangzheng Steel Structure Co., Ltd. is committed to providing different kinds industrial steel buildings of high quality for all customers from all over the world.
A lot of work is needed to promote and improve the design specifications and construction technical standards of different types of structures, and to develop new types of lightweight insulation wall materials and the supporting issues of residential components. At the same time, it is necessary to widely publicize the advantages of the development of Residential steel building, so that more developers, designers and users can understand and understand steel structure housing.
What are the main forms of Residential steel building?
What are the structural characteristics of these Residential steel buildings?
What should I pay attention to when using Residential steel building?
Judging from the Residential steel building that has been built, the king has:
1) Thin-walled steel composite wall panel form;
2) Pure frame form;
3) Frame support form;
4) Form of steel-concrete combination;
5) Steel frame-concrete seismic wall form and so on.
The structural forms of Residential steel building have their own characteristics. Among them, the thin-walled steel composite wall panel is particularly suitable for finalized products. The Residential steel building system evolved from the wall panel structure, that is, the thin-walled steel column members are arranged at a distance of about 600mm. The vertical load-bearing structure and section steel have a support system to resist horizontal forces. The floor slab is arranged as a multi-rib support structure according to the position of the vertical section steel. Because the upper structure is a wall-like structure, the foundation is set as a strip foundation according to the force. The foundation requirements are not high.
The thin-walled steel composite wallboard residence is affected by the dense structure, and there are certain restrictions on the size of the partitions, door, door and window openings, and pick-out components.
The latter several forms of Residential steel building can meet the design requirements of multi-story residential buildings, but there is a common problem from the perspective of use, that is, the impact of the prominent beams and columns on the interior look and feel of the residence.
Compared with other buildings, Residential steel building has its particularity. Offices and workshops can use a relatively fixed column network, and the storey height is also higher. The space occupied by the beams and columns is suitable for people. The rules of the column network are conducive to the beams. Layout. On the contrary, the residence is a product with many changes. According to the requirements of the building, a regular column network is rarely arranged. The interior space of the house is relatively small and changes a lot, which is not conducive to the layout of the steel frame.
After seeing this and learning so much information about residential steel structures, I believe you must also want to order a Residential steel building. Qingdao Xinguangzheng Steel Structure Co., Ltd. can provide the best Residential steel building you need. At the same time, their after-sales service is also very considerate.
Commercial steel building is a new type of energy-saving and environmentally-friendly building system. It is known as one of the "green buildings" in the 21st century. It is an energy-saving, environmentally-friendly, and recyclable building structure.
The general sequence of commercial steel building welding is: pre welding inspection → preheating and derusting → installation and welding of base plate and arc striking plate → welding → inspection
1. Before commercial steel building welding, check the groove angle, blunt edge, gap and staggered joint, and remove the rust, oil stain and iron oxide scale in and on both sides of the groove.
2. Preheating. Before commercial steel building welding, gas welding or special baking gun shall be used to heat the groove and the base metal within 100mm on both sides evenly, and the surface thermometer shall be used to measure the temperature to prevent the temperature from meeting the requirements or local oxidation on the surface and preheating temperature.
3. Recheck the preheating temperature. If the temperature is not enough, reheat it to make it meet the requirements.
4. When assembling and welding the backing plate and arc striking plate, the surface cleanliness shall be the same as that of the groove surface, the backing plate shall be close to the base metal, and the arc striking plate shall be firmly welded with the base metal.
1. Welding: the weld bead of the first layer shall seal the connection between the base metal and the backing plate in the groove, and then weld layer by layer until the groove is filled. After each weld is welded, the welding slag and spatter must be removed, and the welding defects shall be ground away and repaired in time.
2. An interface must be welded continuously. If it is necessary to stop welding halfway, it shall be subject to thermal insulation and slow cooling treatment, and shall be heated again according to the regulations before re welding.
3. In case of rain and snow, commercial steel building shall stop welding. There shall be a wind shield and canopy around and above the welded junction of components. When the wind speed is greater than 5m / s, the welding shall be stopped. When the ambient temperature is lower than zero, preheating and post heating measures shall be taken for construction according to regulations.
4. Carbon structural steel shall be subject to weld flaw detection after the weld is cooled to ambient temperature, and low alloy structural steel shall be subject to weld flaw detection 24 hours after completion.
5. Welders and inspectors of commercial steel building shall carefully fill in the operation record form.
When purchasing commercial steel building, we should pay attention to the design of waterproof, heat-insulating and anti-corrosion of the steel structure. The design documents did not specify the steel derusting grade and paint and coating thickness, and did not adopt corresponding measures according to the different fire resistance limits of different parts. commercial steel building of thermal insulation protection measures needs to be avoided.
Commercial steel building has focused on the development and production of commercial steel buildings for several years. And it commits to provide perfect service for every customer from all over the world.
The main structure of the commercial steel building can be installed simultaneously with the wall panel. The main structure and the wall panel are fixed by embedded parts and connectors, which is convenient for installation. It only needs to be hoisted in place, connected and fixed, and the three links of joint treatment are not required. No need for secondary grouting, and has the advantages of short construction period, high assembly rate, good integrity, and good wind pressure resistance.
(1) When the sides of the upper and lower columns without ear plates are symmetrically welded to 1/3 of the plate thickness by two welders on both sides, cut off the ear plates.
(2) Then two welders are symmetrically welded on both sides to 1/3 of the plate thickness on the side where the ear plate is cut off.
(3) Two welders will be responsible for the welding of two adjacent sides.
(4) The joints of the weld bead between every two layers should be staggered with each other, and the weld bead joints welded by two welders should also pay attention to the stagger of each layer. Pay attention to the temperature between the layers during the welding process.
(5) Welding process parameters:
CO2 gas shielded welding: wire diameter Φ1.2mm, current 280~320A, welding speed 350~450mm/min
Extending length of welding wire: about 20mm, gas flow rate 25~80L/min,
Voltage 29~34V, interlayer temperature 120~150℃
We must prefabricate and assemble commercial steel building steel components on the steel platform in accordance with the installation sequence and process requirements, and ensure the quality of welding production.
The spacing between the splicing seam of the splicing flange plate and the splicing seam of the web plate of the section steel should be greater than 200 mm. The splicing length of the flange plate shall not be less than 2 times the plate width; the splicing width of the web shall not be less than 300 mm, and the length shall not be less than 600 mm.
In order to facilitate the welding of commercial steel building and ensure the welding quality, try to weld the reinforcement plates, connecting plates, backing plates, and overhanging beams (beams) on the columns and beams on the ground steel platform according to the dimensions of the construction drawings.
In addition to the fabrication and assembly of steel components prefabricated on the steel platform according to the construction drawings and specifications, the process and installation dimensions of the commercial steel building on-site installation should also be considered.
The construction of commercial steel building has trained a new generation of construction and installation industrial workers. Factory production and mechanized installation avoid the high dependence of the traditional construction industry on labor, moderately reduce the impact of high labor costs brought on by the aging of the global population on the development of the industry, and predictably cultivate a new generation of construction and installation industry workers. It is of far-reaching significance to the sustainable development of the construction industry.
Qingdao Xinguangzheng Steel Structure Co., Ltd. has focused on the development and production of commercial steel buildings for several years. And it commits to provide perfect service for every customer from all over the world.
The main material of commercial steel building is light steel keel synthesized from hot-dip galvanized steel strip through cold rolling technology. After accurate calculation and support and combination of auxiliary parts, it has reasonable bearing capacity and can replace traditional houses.
What are the progress of commercial steel building?
What is the future development of commercial steel building?
What are the necessary steps in the commercial steel building construction process?
1. The house has good safety performance. commercial steel building is anti-seismic, anti-typhoon, fire-proof and anti-insect and ants. The service life of the main building body can reach 90 years, the overall performance is good, it is not easy to be destroyed by earthquake force, and the building quality and safety performance are better.
2. The house is low-carbon, energy-saving, green and environmentally friendly, and can be reused. The steel of commercial steel building can be recycled and has little impact on the environment during construction and dismantling. Most of the other supporting materials can also be recycled, which meets the requirements of environmental protection; moreover, most of the materials are green building materials, which can meet the requirements of the ecological environment and are beneficial to health.
The steel structure used in commercial steel building will continue to develop into high-strength steel, which will greatly increase its yield point strength; in addition, new types of steel must be rolled, such as H-shaped steel (also known as wide flange steel) and T-shaped steel and profiled Steel plates, etc. to meet the needs of large-span structures and super high-rise buildings.
Steel structure is divided into light steel and heavy steel. There is no uniform standard for judging, and many experienced designers or project managers often cannot fully explain. They can be comprehensively considered and judged based on some data.
1. Purge device
This device uses a high-pressure fan, and multiple sets of elastic blowing nozzles with different angles are arranged in the auxiliary chamber of the chamber to blow and clean the projectiles remaining on the surface of the workpiece.
2. Import and export sealing
The inlet and outlet sealing devices of the workpiece are all made of rubber spring steel plate. In order to prevent the projectile from splashing out of the cleaning room during shot blasting, there are multiple reinforced seals at the inlet and outlet of the workpiece, which are characterized by strong elasticity, long life, and sealing effect. Superb.
3. Dust removal system
The dust removal system is mainly composed of a bag filter, a fan, and a dust removal pipeline. The dust removal efficiency can reach 99.5%.
This is the relevant knowledge about the commercial steel building for you to get more information about it. If you want to order a commercial steel building, you must choose Qingdao Xinguangzheng Steel Structure Co., Ltd., because they can provide the commercial steel building with most high-quality and suitable price.
Prefab House only prefabricates some parts, and it must be poured in the same way as traditional buildings on the construction site. It is not "building blocks" as imagined. Therefore, no difference can be seen from the appearance of the house after it is built. Here we are going to introduce the Prefab House.
What are the reasons why people choose Prefab House?
What are the advantages of steel structure prefabricated houses?
What are the advantages of Prefab House for building plant?
1. Prefab House is of great benefit to energy conservation and environmental protection. Through factory production and on-site assembly construction, it can greatly reduce construction waste and construction sewage, reduce construction noise, reduce harmful gas and dust emissions, and reduce on-site construction and management personnel. Generally, it can save 20% of materials and about 60% of water.
2. The housing industrialization of Prefab House is not only beneficial to the capital flow of development enterprises, but can also increase the speed of housing listing, so it can greatly alleviate the current situation of insufficient market supply and adjust the supply relationship. After large-scale promotion, construction costs can be reduced, and it will also play a role in restraining housing prices.
3. Comprehensive cost accounting shows that the construction cost of Prefab House is higher than that of traditional construction methods, but after large-scale promotion, construction costs can be reduced.
First, the components of prefabricated houses can be industrialized in factories. The components are equivalent to standard products and can be installed directly after being transported to the site. It can be said to be convenient and fast. The construction field during the construction period, especially the unparalleled advantages.
prefabricated houses with steel structure are more stable than those made of welded frame steel. In addition, it is cheaper and more economical. Long service life, 50-70 years. Locked with bolts, it can be used repeatedly without any maintenance.
1. Large span: such Prefab House can realize single span or multi span, and the maximum span without center column is 36m.
2. Low cost: according to the requirements of customers, the unit price of Prefab House ranges from $150 / m2 to $300 / m2.
3. Convenient installation and short construction time: save manpower and cost for customers.
4. Prefab House has a long service life: up to 50 years
5. Environmental protection: such buildings are free of harmful substances.
6. Structural stability: earthquake resistance, wind resistance and snow resistance.
7. Others such as waterproof, heat insulation and energy saving.
The Prefab House produced by Qingdao Xinguangzheng Steel Structure Co., Ltd. has been exported to several countries. And there are several offices in the country, which is convenient for domestic customers to maintain. Based on technological innovation, their company constantly improves product quality and provides you with professional Prefab House.
1. The positioning axis and supporting surface elevation of the foundation are out of tolerance:
The positioning axis of the foundation and the elevation of the supporting steel cylinder exceed the allowable deviation.
The reasons are as follows:
There are errors and deviations in foundation survey control network, foundation survey setting out and elevation finding.
The foundation formwork is not firmly set up, the pouring concrete blanking is too high, and the concrete is vibrated and impacted, which makes the formwork displacement and causes the datum line deviation.
Or the use of steel ruler, theodolite, level without calibration, there are errors.
Or construction wrong drawings, axis wrong, without strict inspection.
Or if the foundation bearing surface is not plastered and leveled twice, the concrete will shrink and sink.
Or the embedded steel plate (or support) is not fixed.
Because the foundation positioning axis and bearing surface are out of tolerance, the column installation axis and bearing elevation will be out of tolerance, which will affect the quality of the whole structural steel construction installation project.
Avoiding measures:
(1) The accuracy of basic survey control network, instruments and measuring tools used for basic survey setting out and leveling shall be accurate. Before use, they must be checked or verified by the measurement department. If problems are found, they shall be adjusted in time to prevent errors or accumulated errors, resulting in axis and elevation exceeding the allowable deviation.
(2) The foundation formwork for steel structure construction must be firmly supported with sufficient strength and rigidity. When pouring concrete, cutting and vibrating, it is necessary to prevent from striking the formwork and causing displacement. In the process of concrete pouring, the positioning axis and elevation shall be checked regularly with measuring tools or suspension lines. If any deviation is found, the pouring and vibration shall be stopped, and the work shall be carried out after reinforcement and adjustment. Before the final setting of concrete, the surface of foundation concrete shall be plastered and leveled twice. For the embedded steel plate or bearing, the elevation and levelness shall be aligned twice, and the concrete at the bottom shall be dense. The steel plate or support of foundation support column shall be provided with necessary fixing devices to ensure correct position and elevation.
(3) When the elevation and levelness of the steel plate or support on the vertical and horizontal axis of the foundation and column bearing surface are out of tolerance, measures shall be taken according to the degree of deviation. When the out of tolerance is not serious, it can be solved by shifting the column base, reaming and packing the base plate. If the deviation is serious and cannot be adjusted, it should be studied with relevant departments to work out a feasible correction scheme before treatment.
2. Foundation anchor bolt thread damage:
The foundation anchor bolt thread is damaged, and the nut cannot be screwed and tightened during the column installation.
The causes of bolt thread damage are as follows:
Anchor bolts are impacted or improperly kept during transportation, loading and unpacking, resulting in serious thread corrosion.
Or the bolts were not protected after burying and were damaged by outside.
Or the bolt is used as electric welding zero line on site, and the thread is damaged due to arc burn.
Or the bolt is used as the binding point of the pulling force of the traction rope.
Due to the damage of bolt thread, it is impossible to screw in nuts to fasten steel columns and other components, which affects the transmission and stability of structural force.
Avoiding measures:
(1) When the anchor bolts are transported, packed and unpacked, the thread protection shall be strengthened. After being smeared with industrial vaseline oil, they shall be wrapped and bound with plastic film to prevent thread damage and corrosion. And should be stored separately, should not be mixed with other parts and components, so as to avoid mutual impact damage thread.
(2) After the anchor bolt is embedded, it shall not be used as the fulcrum of bending processing, the neutral line of electric welding machine, or the binding point of traction force. When lifting components, proper operation shall be carried out to prevent the thread from being damaged by horizontal lateral impact force.
(3) The screw thread of the bolt has been damaged, and the following treatment methods can be adopted: when the damaged length of the screw thread does not exceed its effective length, the steel file can be used to trim the screw thread, so as to smoothly screw in the nut. When the length of thread damage of local foot bolt exceeds the specified effective length, the length of original thread section can be cut by gas cutting; Then, with the same material and specification as the original bolt, one end of the bolt is processed into thread, and the butt end section is made into 30º-- 45º. After butt welding with the lower end of the groove, the corresponding diameter specification and length of the steel casing sleeve into the joint, welding reinforcement. After casing reinforcement for steel work in construction, the diameter of the bolt will be larger than that of the base plate, which can be solved by appropriately enlarging the diameter of the base plate.
3. The setting of mortar base plate of column base does not meet the requirements:
The mortar base plate of column base is set randomly, and the elevation, levelness and position do not meet the design and specification requirements.
The reasons are as follows:
The surface of the foundation is not treated and leveled, so that the base plate can not bear the force smoothly, and the surface is uneven and uneven;
The base plate is not reasonably arranged according to the stress requirements, so that the base, base plate and foundation can not bear uniform pressure, so that the settlement of base slurry is uneven, and the elevation and levelness can not meet the requirements.
If the setting of open base plate does not meet the requirements, it can not transfer the load evenly, which will reduce the mechanical performance of the column and affect the stability of the superstructure.
Avoiding measures:
(1) In order to make the base plate group transmit the force to the foundation smoothly, the base plate should be closely combined with the base slurry on the foundation surface. The uneven foundation surface shall be chiseled and leveled.
(2) The location and distribution of the base plate should be correct. Generally, according to the stress area of the steel column base plate, the base plate, the base plate and the foundation should be arranged in the center of the steel plate and the stress concentration position on both sides or near the two sides of the anchor bolt, so that the base plate, the base plate and the foundation can fully bear the pressure load, and bear the force uniformly together to avoid partial bias Concentrated stress or deformation of the base plate occurs when the anchor bolts are tightened.
(3) The area of the base plate directly bearing the load should meet the needs of the stress, which should be determined by calculation, and the area should not be too large or too small. Too large will cause waste, too small will cause local concentrated overload of foundation and affect the overall and uniform stress of foundation. The thickness of the base plate is generally within the range of 4 ~ 25 mm, each group is no more than 3 pieces. The base plate has a 10 ~ 12 mm thick steel plate, the length of the base plate is 100 ~ 300 mm, and the width is 50 ~ 120 mm. When setting the mortar, use non shrinkage cement mortar with strength not lower than 30MPa. As the steel column is mainly installed with cushion plate to adjust the elevation and levelness, the elevation and levelness shall be found when grouting, and the allowable deviation shall comply with the specification, and the supervision shall be strengthened. Before the base plate is grouted, the rust, oil stain and burr on the surface of the base plate shall be cleaned, so that the base plate can be firmly combined with the concrete when grouted and grouted; The length of the base plate group exposed to the outside of the base plate edge is about 10 ~ 20 mm.
4. Before the installation of steel column, the foundation is directly installed without inspection:
Before the installation of steel column, the axis and elevation of the foundation, the position and elevation of the anchor bolt and the concrete quality of the foundation are not checked in advance, so the installation is carried out directly. In this way, there may be out of tolerance without repair, which will cause structural installation difficulties, increase the steel column installation stress and affect the installation accuracy, and even cause quality hazards.
Avoiding measures:
Before the installation of steel column, the positioning control line, foundation axis, elevation, anchor bolt position, elevation and concrete quality of foundation shall be pre checked. If the deviation is found, measures shall be taken to correct and adjust to the allowable deviation range of the specification. For elevation inspection, the measured data shall be compared with the pre inspection data of steel column size and elevation, and the error of the two shall be eliminated when the support base slurry pad or anchor bolt nut is adjusted. The allowable deviation of foundation support surface, anchor bolt position and base slurry pad shall meet the requirements of the specification. The quality of foundation concrete shall be dealt with in accordance with relevant regulations.
5. Don't check the dimension of steel members, deal with deformation and quality defects before installation
Before the installation of the structure, the external dimensions of the steel members are not checked, and the deformation and quality defects of the members are handled.
Although the steel components have passed the quality inspection before they are processed in the factory, they may fail to be inspected, or new deformation and damage may occur in the transportation and stacking of the components. If the review is not carried out before the installation, these problems can not be dealt with in time before the installation, which will affect the installation quality of the steel structure and cause installation difficulties or permanent quality defects.
Avoiding measures:
Before the installation of steel members, the steel members shall be carefully checked in advance:
It includes checking the model and quantity of the component, the overall dimension of the component, the relevant dimensions between the supporting surfaces and the installation holes, and marking the datum line of the axis of the component. Check whether the component is deformed, and correct and repair the deformation error if there is any.
Whether the connecting plate, splint and other accessories of the component are complete and whether the position and size are accurate. Inspect whether the surface quality of the welding area of the component and the friction surface of the high-strength bolt connection meet the requirements and whether it is polluted.
Whether the member nodes are complete and whether the center of gravity of main components is marked.
Whether the surface of the component is polluted, whether the paint falls off, etc.
Pre inspection records of components shall be made; For the components with deformation and defects exceeding the allowable deviation, they shall be corrected and repaired on the ground before installation, and can be installed after they are qualified.
6. The perpendicularity of steel column installation is out of tolerance:
The verticality deviation of steel column exceeds the allowable value in design or code
When the steel column is manufactured, the deformation control measures are not taken or the bending deformation is not straightened.
Or the length of the column is large, the rigidity is poor, and the elastic or plastic deformation occurs under the action of external force.
Or due to the unreasonable hoisting technology and procedure, the roof panel is bent and deformed under the action of temperature, wind and external force.
Or there is deviation in the span size of the roof truss, the external force is used to force the connection during the installation, resulting in the over deviation of the verticality of the steel column.
This will lead to the deflection of the steel column and affect the bearing capacity and stability.
Avoiding measures:
(1) Anti deformation measures shall be taken for assembly and welding of steel column, and the deformation during fabrication shall be corrected in time. When transporting and stacking steel columns, the supporting points should be appropriate to prevent bending deformation under the action of self weight. The out of plane stiffness of long column is poor, so the lifting point should be selected at 2 / 3 of the total length of the column to prevent deformation. If the span size of steel roof truss exceeds the deviation, it should be corrected before installation to prevent forced connection and bending deformation of column body.
(2) When the steel column is hoisted to the foundation plane in place, the vertical and horizontal axis above the column base plate should be aligned with the foundation line, so as to prevent the deviation of span size, which will lead to the horizontal tension or thrust when the column head is installed and connected with the roof truss, so as to make the column body bending and deformation, and carry out appropriate control.
(3) When the roof slab is hoisted after the connection and installation of the steel column and the tail-stock, it should be carried out symmetrically and synchronously from the edge of the two slopes in the center of the top chord to the middle, so as to prevent the bending deformation of the steel column caused by the lateral concentrated pressure generated by the one slope. Without the permission of the design, the steel column and other connected components shall not be used for horizontal dragging or vertical hoisting of heavy components and equipment, and the column bending deformation or damage to the connecting structure shall be prevented.
(4) If the bending steel column is elastic deformation, it can be restored to its original state after the external pressure is removed; If it is plastic deformation, it can be corrected by adding temporary support above or at the top of the bending part of the steel column before correction, so as to reduce the load-bearing gravity, and then fixing one side reaction frame at the bending part, and using jack for correction. If the rigidity of the steel column is large, it can be corrected by heating the bending convex surface with oxyacetylene flame, and then applying jacking force.
7. Steel column installation height is out of tolerance:
Height dimension or relative position of steel column after installation (±) The elevation dimension is out of tolerance, which makes the difference between the total height of each column and the height deviation of the bracket.
The reasons are as follows
Foundation elevation is incorrect or deviation occurs.
The length and dimension of steel column during the production stage are out of tolerance.
Or when the foundation elevation is adjusted and treated during installation, it is not combined with the actual length (height) of steel column, which will cause the positive or negative difference of the height dimension or elevation dimension of the steel column after installation.
Because of the over tolerance, it is difficult to install and adjust the components connected with it, which makes it difficult to correct and takes time.
Avoiding measures:
(1) During the foundation construction, the elevation size should be strictly controlled to ensure the accuracy of elevation. The elevation dimension of the upper surface of the foundation shall be adjusted according to the actual length of the steel column or the elevation dimension of the bracket supporting surface, so as to make it consistent with the height and elevation dimension of the steel column after installation.
(2) During the manufacturing process of steel column, the length and size (including the total length and the length of each position specified in the design, the length and size within the allowable positive and negative deviation range, and the positive excess value not allowed) and the correct size of the total length and bracket of the steel column without contact point shall be strictly controlled. The latter can be adopted to weld the column body first, and the column base plate and column head plate shall not be welded temporarily, In case of out of tolerance, adjust before welding the base plate or upper column head plate of the column, and finally weld the base plate and column head plate of the column.
Residential steel building is a residential system composed of an envelope structure and a steel supporting structure. It is a new type of energy-saving and land-saving residential system. Its steel structure residence abandoned solid clay bricks and effectively used land resources. Compared with traditional houses, steel structure houses have advantages in terms of use function, design, construction and comprehensive economy.
What are the reasons why people choose Residential steel building?
What should the choice of Residential steel building structural system look like?
What is the framework system used by Residential steel building?
1. Residential steel building energy saving and environmental protection
The main body of the Residential steel building is steel components, and the wall material is thermal insulation mortar, which not only meets the requirements for energy saving, but also can be recycled. It is a green and environmentally friendly recycling building that meets the requirements of sustainable development. The thermal resistance can reach a brick wall thickness of about 1m. At present, the global population is large and energy consumption is large, and the promotion and application of steel structure housing is the final choice.
2. Residential steel building's pipe network line layout is convenient
In residential buildings, there are many lines of professional plumbing and electricity pipe network, which will reduce the effective use area in traditional buildings. In Residential steel building, there are many holes or holes in beams and columns, which is easy to form a cavity for wiring layout. Moreover, the beam can be artificially made into a honeycomb shape, which is convenient for line layout, which not only saves the net height of the building, but also increases the use area.
According to engineering practice, the commonly used Residential steel building structure system can be selected with reference to the following scope:
The 4th to 6th floors are the steel frame system, the steel frame-support system, and the steel frame-shear wall system; the 7th to 12th floors are the steel frame-concrete core tube (shear wall) system.
The section form of steel components should be hot-rolled H-section steel, high-frequency welded H-section steel and steel tube concrete.
Light steel frame system
The light steel frame system is a load-bearing frame composed of hot-rolled H-shaped steel (or I-beam), high-frequency welded H-shaped and cold-formed square pipes, and a steel structure residence with composite curtain walls or infill walls as the enclosure structure system.
The wall panels in the picture collection are made in the factory with fly ash as the filler, sulfoaluminate as the cement, polystyrene foam (EPS) as the core material, and glass fiber mesh as the reinforcement material. A lightweight board. Special adhesive is used to bond the plate and the light steel frame, and between the plate and the plate. To prevent thermal bridges using double-layer plates.
Qingdao Xinguangzheng Steel Structure Co., Ltd., as a leading company in China's Residential steel building, has committed to providing the most suitable Residential steel building at a reasonable price, and whatever it takes to satisfy the customer’s needs.