











Production introduction of Steel Structure AUDI Showroom and Workshop
Project Name: Audi Showroom and Workshop
Project Area: 4600 m2
Project address: Montevideo Uruguay
Project Details:
1. Showroom: Roof beam is truss structure, column is Box steel
2. Workshop: Roof beam is H section steel, column is H steel.
3. Wall Panel: Horizontal-Assembling PU Sandwich Panel
4. Roof Panel: EPS Sandwich Panel
Introduction of Maldives Prefabricated Steel Structure Construction Mall Building Hardware Store:
Project Area: 3323 ㎡
Project Date: 2017
Project Detail: Six-story steel structures, 100mm fiberglass wool sandwich panel for roof and Glass Curtain +Aluminum Wall Cladding for outer wall and 75mm rock wall sandwich panel as inter wall. The fireproof grade is grade 2, and the fireproof coating is indoor thin fireproof coating.
Effect picture of Maldives Prefabricated Steel Structure Construction Mall Building Hardware Store :
Company information
Qingdao Xinguangzhegn steel structure group company has 1200 workers, 360000 ㎡ non-dust workshop, 25 years experience, CE, ISO9001, ISO9712, ISO3834, BV, SGS certificated, one hour reach Qingdao port, our company, as a manufacture, this is how we keep good quality and competitive prices for global valued customers.
We provide steel building design, farm house design, manufacture and installation service.
Steel structures are a new type of construction system that offers the benefits of low weight, easy installation, short construction time, good seismic performance, fast investment recovery and low environmental pollution. It is therefore generally preferred by all parties in the industry. Under the call for green construction, energy saving, environmental protection and resource recycling, steel structures have gradually become widespread in agricultural steel building and the scale of the steel construction industry has expanded further.
What are the requirements for the operating equipment of agricultural steel building?
What are the technical requirements for agricultural steel building?
What are the construction requirements for agricultural steel building?
1. The machinery and equipment of the agricultural steel building are operated and maintained by designated personnel, and the operating certificates are complete.
2. Mechanical operation part and on-site electricity requirements:
a. The rotation and dangerous parts of various machines and electric machinery must be equipped with protective devices.
b. Electrical equipment and wiring must be well insulated, with rain-proof and moisture-proof facilities.
c. The electrical box has a door, color code and number, which meet the installation height. The high-voltage leakage protector and zero grounding are complete. The switch box and electrical equipment must be "one machine, one switch, one leakage", and the fuse and actual equipment load Match.
d. When installing electrical equipment, the switches, circuits, grounding devices, etc. must be inspected, and they must be intact and undamaged, with good insulation.
(1) The agricultural steel building has a reasonable structure, a 360-degree undercut connection, and no bolts on the roof, which completely avoids water seepage and water leakage.
(2) Adopt self-fixing bolts to fix, simplify the operation and greatly reduce the labor intensity of workers. There is no need to set up a scaffold fixing nut, which improves the safety of operation.
(3) The boom of agricultural steel building is detachable and the angle can be adjusted freely, which is suitable for simultaneous construction of arch roofs with multiple spans.
1. First, according to the functional requirements of agricultural steel building, adopt a corresponding reasonable structure system. Achieve advanced technology, novel structure, and achieve the unity of architecture and structure.
2. The agricultural steel building is mostly based on rods, so the size of the rods is as modular and standardized as possible, which is convenient for mechanized manufacturing, transportation, installation, and improves productivity.
3. The agricultural steel building adopts high-efficiency steel with high economic indicators.
4. The nodes of agricultural steel building are very important. Appropriate connection methods should be adopted to make the node design consistent with the simplified structural calculation model. In the past, most of the structural damage occurred at the nodes, so the nodes must be carefully designed and constructed. Advanced and reliable connection methods are used.
Qingdao Xinguangzheng Steel Structure Co., Ltd. employs more than 100 workers, through the efforts of their entire staff, the agricultural steel buildings of high quality, widely used in a variety of architecture, have shared the broad masses of the worldwide market for over a decade.
The full name of MDC is"MONDU DA CASA (home world)", which is constructed by Qingdao Xinguang Zheng Steel Structure Co., Ltd. This is a comprehensive shopping center centering on the theme of "happy home". This theme is the same as the enterprise mission of "benefiting the society, achieving employees and making customers happier". In addition to "home world", she has another interpretation of "modern decoration Center".
MDC is located in KIKUXI section of Luanda expressway, surrounded by Angola national stadium, high-end residential villa area, Brazil nursery garden, and Luanda commercial pedestrian street under planning, with superior geographical environment and convenient transportation.
"MDC home world" shopping center covers an area of about 30000 square meters. Relying on the global procurement network, it has gathered kipor generator 4S shop, furniture store, building materials store, home furnishing store and home appliance store. The categories include building materials pipe fittings, wood, floor tiles, paint and coating, decorative lamps, kitchen and bathroom equipment, hardware tools, electrical and electrical materials, gardening supplies, cloth furniture, home appliances, etc., and also auxiliary It is one of the most comprehensive "one-stop purchasing" centers for home furnishings in Luanda with public service facilities such as business office, catering, leisure and entertainment, bank, etc.
Ⅰ. Steel column installation for steel structure construction
1. Installation sequence of steel column:
① Foundation setting out → ② binding → ③ hoisting → ④ correction → ⑤ final fixation
2. Installation method of steel column:
(1) Setting out:
A. Elevation control:
In this structural steel construction project, iron parts and "middle bars" are controlled according to the depth of concrete cup mouth, the elevation of steel column bottom and the embedded elevation in the center of the bottom of the cup mouth during the construction of concrete foundation (φ30 steel bars), the elevation of top surface of "middle reinforcement" is based on the elevation of steel column bottom, and the elevation error of iron parts is controlled in ± Within 1mm.
To ensure the steel column is embedded in the foundation accurately and firmly φ On the 30 "middle reinforcement", weld a steel plate with thickness of 20 at the bottom of H-shaped steel column, as shown in the figure below.
When installing structural steel column, clean the foundation cup mouth first, and check the embedded elevation control "middle reinforcement" in the foundation(φ The actual height of 30 steel bars) is not necessary because the elevation embedded in the foundation construction has been controlled precisely, and no additional iron pad is needed. The method is simple, fast and efficient for the treatment of steel column feet. The construction is fast and the force is reasonable. When the column is lifted, it can be adjusted freely in several directions when the elevation is unchanged.
B. Before installation, the vertical and horizontal axis reference lines of the foundation plane shall be placed on the top of the cup mouth by woodworking ink bucket as the installation and positioning line of steel column.
(2) Column binding and hoisting:
A. after the steel column enters the site, the steel column shall be arranged according to the position of the lifting plan, and the model and number shall be checked to see if they are correct. The plane position of steel column after entering the site is shown in the following figure.
B. Before the column is lifted, a horizontal line shall be drawn with red oil paint 2300mm upward from the bottom of the column, so as to recheck the plane elevation datum before and after the installation and fixation.
C. the column installation belongs to vertical hoisting. In order to keep the suspended column drooping and facilitate the positioning, the binding point is determined at the lower part of the bracket. In order to prevent the sharp edges and corners of the column edge from damaging the lifting rope during hoisting, the rubber belt of the old car is used to separate and cover the edge and corner lifting rope. Pay attention to binding firmly and easy to remove.
D. temporary steel ladder and high-strength bolt installation fixture of working platform shall be bound on the steel column.
E. in order to avoid the free swing of the suspended column, hemp rope should be used to tie the upper part of the column bottom as a restraint rope and adjust the direction.
F. according to the site conditions, the rotation method is adopted for hoisting
After the preparations before hoisting are ready, the trial hoisting shall be carried out first. When the height of the steel column is 200 mm above the ground, the hoisting shall be stopped to check whether the rigging is firm and whether the crane is stable. After confirming that there is no problem, the crane can be directed to slowly lift, rotate to the top of the cup mouth, and then slowly descend. When the distance between the bottom of the column and the design position is 40-100 mm, adjust the two datum lines of the column body and the foundation to reach the accurate position, direct the crane to descend to the position, and temporarily fix the column with steel wedge (or wood wedge) and wind rope to remove the hook.
• Key points of rotation method:
The method of lifting the column by rotating the column around the column base is called rotation method, as shown in figure a below. When the column is hoisted by rotation method, in order to improve the hoisting efficiency, when the steel column enters the site, the binding point of the column, the center of the column base and the center of the cup foundation should be placed on the arc with the crane stop point as the center and the distance from the stop point to the binding point (i.e. the turning radius of the column), as shown in Figure B below.
The steel column hoisting is shown in the figure below:
(3) Preliminary correction of column:
The column should be corrected on the side with large deviation first, and then on the side with small deviation.
A. The correction of column generally includes plane position, elevation and perpendicularity.
B. When the steel column is hoisted in place, it is one-time alignment, and generally it does not need plane re correction. For the elevation of the column, it has been used before hoisting φ The embedded "middle reinforcement" can accurately control the elevation. Generally, it only needs to be checked, and it does not need to be corrected. Therefore, the steel column correction is mainly to correct the verticality and recheck the elevation.
C. In this project, the perpendicularity of the column is observed, and two theodolites are used for measurement and correction.
• First, place the theodolite on one side of the column, align the longitudinal center wire with the baseline of the column base, and then fix the screws of the horizontal plate.
• Measure the center line of the column and observe from bottom to top. If the vertical center line is aligned, that is, the column is vertical. If it is not aligned, the column shall be adjusted until it is aligned with the longitudinal center line of theodolite.
• Measure the horizontal line in the same way so that the center line of the other side of the column is perpendicular to the horizontal axis of the baseline. After the column is accurately positioned, the column can be fixed.
• Verticality correction of steel column: distance adjusting screw rod and steel wedge are used. Due to the small contact surface of the long side of the column, the base plate is set during the construction. The details are as follows.
The manufacturing dimension of steel wedge is shown in the figure below:
(4) Final alignment and fixation of steel columns:
After the steel column is hoisted in place, the column correction mainly involves the adjustment of elevation and the correction of verticality; The correction method can use tools such as wind rope, Jack, crowbar and steel wedge (or wooden wedge) to apply vertical force and lateral force of pulling, jacking, supporting and prying to the steel column.
Adjust the verticality, positioning axis and elevation of the column. After confirming the correctness, the gap between the steel column and the foundation cup mouth shall be poured with C40 fine stone concrete. The expansive high strength grouting material is preferred.
Ⅱ Protection of site components:
1) The unloading of components shall be careful to prevent damage and prevent collision and extrusion between members.
2) The members shall be stacked in order at the designated site, and the number of layers stacked by steel beams shall not exceed 3 layers to prevent the members from squeezing and deformation.
3) Before hoisting, oil, sediment and dust on the surface of the components shall be cleaned.
Ⅲ The placement of components and the requirements for the site
1) When unloading, the components are unloaded directly near the installation position and within the radius of rotation of the crane. Mark the number clearly with a clear color pen to facilitate lifting.
2) The components are placed in order in the site, and a certain gap is reserved between adjacent components to facilitate binding.
3) The site shall be solid and flat, and the components shall not be polluted due to rain and snow, and the vehicle with 30 ton level can be walked.
Ⅳ Steel structure building installation
Preparation before hoisting of steel column:
Before hoisting the steel column, the cable wind rope shall be tied to the column body. The lifting point shall be at the bracket position, and the double wire rope shall be set up and down, and the snap ring can be checked to be qualified before entering the next work. Before hoisting the steel column, the positioning axis, foundation axis and elevation, cup opening size and the height of the bottom standard of the steel column must be inspected and handed over and accepted. The number, outline dimension, screw hole position and diameter of the steel column shall be comprehensively reviewed. After confirming that it meets the requirements of design drawings, draw out the installation center line and the lower end elevation line of the steel column.
Ⅴ Steel column hoisting
(1) installation method of steel column
Before lifting the steel column, the wooden board shall be fixed at the column foot to prevent damage to the column foot and other structures.
Special hoisting steel wire rope is used for steel column binding. Wood or rubber sheet shall be used to prevent damage to the steel column.
The steel column is installed by a 25t truck crane. When the steel column is lifted, the crane shall hook and rotate the arm while lifting the steel column to make the steel column vertical away from the ground.
(2) positioning adjustment and temporary fixation
When the steel column is lifted to 200mm above the base cup mouth, it will be stable, and it will fall slowly at the base cup mouth. Avoid hitting the concrete edge of the foundation cup mouth during falling. After implementation, use special angle ruler to check, adjust the steel column to make its positioning line coincide with the foundation positioning axis. Three people are required to operate the adjustment, one person moves the steel column, one person helps to stabilize and the other person conducts the test. The positioning error is controlled within 2mm.
(3) when adjusting the elevation of the steel column, place the pad iron at the bottom of the cup foundation, use the level to super level the bottom plate elevation of the steel column as the top elevation of the pad iron, so that the elevation after the steel column is in place can meet the design elevation requirements, mark the elevation datum point on the column body, and then use the level to measure the installation elevation after it is installed in place.
(4) the verticality of the steel column shall be preliminary adjusted by the level ruler. Then two theodolites are used to observe from both sides of the column at the same time, and the adjustment is carried out by relying on the cable wind rope. As shown in the figure below:
Diagram of verticality adjustment of steel column
(5) after the adjustment, use eight iron wedges to position the gap between the bottom of the steel column and the base of the cup mouth, and then spot weld the column to make it stable.
Ⅵ Steel beam installation
Steel beams must be stacked in order on site for this steel work in construction. Sleepers must be placed in the middle of each layer of steel beams. Two lifting points for steel beam hoisting are selected on both sides of the center of gravity of the steel beam. The two lifting points should be 800mm away from the support and the middle of the span, and the distance between the two lifting points should be increased according to the length of the steel beam.
To ensure safety and prevent the sharp edge of the steel beam from cutting the steel wire rope, the steel wire rope shall be protected, the angle of the sling shall not be less than 450, and the steel beam shall be directly tied and rolled with the steel wire rope or lifted with a special fixture.
Before hoisting the steel beam, install the safety rope on the steel beam. When hoisting, hang two sliding ropes at both ends of the steel beam. Two people pull two sliding ropes respectively. The hoisting speed of the steel beam must be slow. In order to ensure safety, personnel should not stand directly under the beam. The cloth bags specially used for placing high-strength bolts are put on both ends of the steel beam. When the steel beam is hoisted above the position, the steel beam is put in place. The falling speed of the steel beam is controlled at 3m / min. two installers are arranged at both ends of the steel column head to prepare for the installation of the steel beam. When the steel beam is close to the in place position, two installers should hold the upper flange of the steel beam with their hands respectively, drag the steel beam to the in place position, and prepare to install the high-strength bolts.
Ⅶ Installation of retaining structure and support corner brace
1) Installation of roof purlin: when the main structural steel forms a frame section, the roof purlin is hoisted to the main beam of the roof with a crane and installed manually. The purlin can also be manually pulled onto the roof with a white synthetic rope for installation. After the installation of purlin, the purlin support is installed in time.
2) Wall purlin installation: when the main structure forms a frame section, the construction personnel stand on the scaffold platform and pull the wall purlin to the installation position with white comprehensive rope.
3) Corner brace installation: after the main body is welded, the corner brace is connected.
Ⅷ Measurement and correction of steel column
Verticality correction of steel column
When the steel column is installed and corrected, two theodolites are set up on the control line with 90 degree translation of 1 meter each other, and the theodolite operators observe the small steel ruler on the top of the column, measure the deviation of the steel column and direct the correction.
A. Control the verticality of the steel column between the first hoisting joints.
B. Steel column calibration is divided into four steps:
initial calibration during initial tightening; Re-calibration before final tightening; Tracking and monitoring during welding process; Final result measurement after welding.
The perpendicularity can be roughly controlled with a long level before the initial tightening, and it can be accurately corrected after the frame is formed. After welding, retest shall be carried out, and the measurement results shall be compared with those at final tightening, so as to be the basis for the next construction.
C. Verticality measurement method of C steel column
Initial correction: the perpendicularity of the steel column is preliminary adjusted with a level ruler.
Accurate correction of steel column perpendicularity: one column grid is used as an installation section for the hoisting of the main frame until the hoisting of three continuous complete sections is completed
After the whole is formed, the measurement correction can be inserted. Two theodolites are used to observe from both sides of the column at the same time, and the wind rope is used for correction and adjustment.
Ⅸ Steel structure survey
2) Elevation control of steel column
Based on the elevation reference point of the plane layer where the steel column is located, the deviation value of the horizontal elevation of the steel column is measured with the level gauge and the correction is directed.
3) Steel beam measurement
After the steel column is hoisted and corrected, the +1.00m control point shall be measured to each steel column according to the site level as the basis for vertical transfer of elevation and the elevation of beam installation; Pop up the center line of the steel beam on the surface of the steel beam.
The control axis is measured to the column body to control the beam position offset; The accuracy of beam elevation is controlled according to the control point of column elevation. Set up theodolite on the floor platform, and then look at the cross angle to the axis of the corresponding beam. Aim at the center line of the upper surface of the beam to the other end with theodolite to see if the number coincides with the axis of the beam.
Calculation of survey and lofting data
In this project, the computer automatic query method is used to calculate the survey and lofting data. The specific steps are as follows:
1) The establishment of data model
Firstly, according to the design coordinates and the dimension relationship of each building in the design drawing, the building, building axis, control line to be lofted and so on are drawn in AutoCAD according to the proportion, and the data model is established.
2) Survey and lofting data query
After drawing the survey loft data model, the survey loft data such as the angle and distance between the known basis (axis control pile, lofted axis, etc.) and the control line to be lofted are queried by using the command of dist of AutoCAD.
3) Advantages of computer automatic query
The method of computer automatic query is used to obtain the required measurement and positioning data. It is not only convenient to calculate, but also has high precision. The distance precision can be set to 0.1mm, 0.01mm, and the angle precision to 0.0 ", 0.00" or higher according to the actual situation.
Ⅹ Construction of high strength bolt
1. Preparation before installation
1) Test and inspection of high strength bolt
Anti slip coefficient test
The project adopts class 10.9 large hexagon high-strength bolts. The anti slip coefficient test of high-strength bolts shall be conducted by taking the most representative thickness of the plate in the project for test, and three groups shall be made.
The size of the specimen plate is as follows:
Axial force test
Randomly select the bolts to be installed at the construction site, and 8 sets of bolt pairs are selected for re inspection in each batch.
2) Transportation and storage of high strength bolts
transport
The form, size and technical conditions of high-strength bolt connecting pair shall be manufactured and supplied by the manufacturer according to batch, with factory certificate and high-strength bolt connection pair, which shall conform to the provisions of national standards gb1228-1231-84 and gb3632-3633-83. High strength bolts with large hexagon for steel structure
The connecting pair consists of a bolt, a nut and two washers. The combination of use shall meet the national standards, and the high-strength bolt connection pair shall be supplied with storage and transportation in the same batch.
The high-strength bolt connecting pair shall be installed and placed lightly during loading, unloading, transportation and storage to prevent the packing box from being damaged or damaged.
Storage of high strength bolt warehouse
1. the high-strength bolt connection pair shall be cleaned according to the specification, batch number and supply date of the packing box, and shall be kept in the indoor warehouse, and the accumulation shall not be higher than 3 layers. The indoor moisture-proof, long-term dry, rust and dirt contamination shall be prevented, and torque coefficient shall be prevented from changing. The bottom layer shall be more than 300mm above the ground level.
2. when installing on site, the quantity of high-strength bolts required on the day shall be issued. The rest should be kept properly. Do not put it in disorder, damage the thread, and be contaminated with dirt.
3. before using the long-term storage high-strength bolt connection pair, a comprehensive quality inspection shall be conducted again. If any abnormal phenomenon is found after unpacking, the inspection standard shall be conducted according to the relevant provisions of national standards gb1228-1231-84 and gb3632-3633-83. It can be used after being qualified.
3) Construction management of high strength bolts
1. Construction Manager
When carrying out the construction of this high-strength bolt, the high-strength bolt manager shall be determined first to be responsible for the project management, quality management and guidance of the construction personnel.
2. weather management (climate conditions)
In principle, no operation shall be carried out during rainfall and snowfall. If rain or snow fall occurs during operation, the speed shall be accelerated to lock the unfinished ones
3. friction surface management
Before tightening, the friction surface shall be inspected first. If there are any attachments to reduce bearing capacity of friction surface, such as rust, oil, paint and residue, metal brush, sandpaper and oxygen acetylene flame shall be used for removal.
4) Construction of high strength bolts
1. final tightening of temporary bolts
Before inserting high-strength bolts, temporary bolts shall be used to tighten the connection tightly, if the materials of the connection parts are bent or warped, they shall be corrected.
If the difference of holes is within 2mm, it can be corrected by cutter.
If the difference of holes exceeds 2mm, reasonable treatment methods such as replacement of panel shall be adopted based on consultation with management personnel, and gas cutting and reaming are not allowed.
2. high strength bolt insertion
The nut and gasket of high-strength bolt shall pay attention to the installation direction, and install according to the following figure.
When inserting bolts, pay attention not to attach rust, dust, oil, etc. to the bolts. In addition, do not force into the bolt hole during construction to avoid damaging the thread.
3. initial tightening
After the temporary fixing bolts are locked, confirm the compactness of the components.
After initial tightening, mark with white marker through bolt nut, gasket and component.
When using the inspection wrench, although the torque value can be confirmed by the contact sound, it is easy to over tighten if the mechanism continues to apply force, so it should be noted.
4) Final tightening
After initial tightening, use special fastening wrench to lock until the neck is broken.
In principle, the bolts inserted on the same day shall be screwed out on the same day.
The advantages of industrial steel building are high seismic performance, good fire resistance, short construction period, and durability. Compared with traditional factory buildings, industrial steel building has improved a lot, so it is strongly welcomed by the market.
What are the types of single-structure industrial steel building?
What are the advantages of single-structure industrial steel building?
What are the advantages of industrial steel building construction?
1. From the height:
The height of the drip level of a single-storey factory building is very important. Some factory buildings are 4-5 meters high, some are 6-7 meters, and some can be as high as 11-12 meters or higher. Generally, the taller the factory building, the more difficult it will be to build, and the more expensive the material costs will be.
2. From the external building structure:
Simple iron sheet: It is the simplest, a factory built with iron sheet relatively freely.
Steel structure workshop: The steel structure workshop is divided into steel structure or ordinary steel structure. Color steel structure is more than ordinary
much better.
Concrete structure: The wall is built with bricks and the roof is sealed with concrete. This structure has better safety and heat insulation than the previous two.
3. From the internal structure:
It is divided into those with corbels and those without corbels. Only the workshops with corbels can install cranes (also called cranes). This is an important part of industrial production. If there are machinery and equipment to install cranes, just Must have corbels to use.
industrial steel building has the characteristics of forming a large space for use, easily meeting the requirements of the production process, and convenient internal transportation organization, which is conducive to the placement of heavier production equipment and products, and can realize the industrialization of the production of plant building components and the mechanization of on-site construction. Therefore, industrial steel building has been widely used in industrial buildings such as metallurgy, machinery manufacturing, motor manufacturing, chemical and textile industries. Common structural forms of reinforced concrete single-story factory buildings include bent frame structure and rigid frame structure.
1. industrial steel building has good structural performance, light weight, high strength, and good seismic performance.
2. The steel used in industrial steel building is recyclable, which is more energy-efficient and environmentally friendly than masonry and concrete.
3. The industrial steel building is processed by the factory, so the quality of the industrial steel building is guaranteed.
4. industrial steel building materials have light weight and low base cost.
5. The on-site construction period of industrial steel building is short. There is basically no wet work on site, and no dust, sewage and other pollution will be generated.
6. The cross-section of structural components is small, the pillars are very thin, the walls are very thin, and the building area is large.
Qingdao Xinguangzheng Steel Structure Co., Ltd. has been committed to providing customers with reliable industrial steel buildings and perfect after-sales service so that customers can invest easily, use them with confidence, and have no worries.
Agricultural steel building is a construction of steel materials and is one of the main types of construction. The structure consists mainly of steel bearings, steel columns, steel works and other components made of profile steel and steel plates and uses silanisation, pure manganese phosphation, washing and drying, galvanising and other rust and rust protection methods.
What is agricultural steel building?
What are the characteristics of people who opt for agricultural steel building?
What are the benefits of people opting for agricultural steel building?
The agricultural steel building is characterized by high strength, low weight, good overall stiffness and high deformation resistance. It is therefore particularly suitable for the construction of large-scale and ultra-high agricultural buildings; The material has a good homogeneity and isotrope, which is ideal for elasticity. The structure most closely corresponds to the basic assumptions of general technical mechanics; the material has good plasticity and toughness, can exhibit large deformations and can withstand dynamic loads well; construction time is short; the agricultural steel industry has a high degree of industrialisation and can be specialised in agricultural production.
1. agricultural steel building has good sealing performance
Since the welding design can be completely sealed, it can be air and water-tight to high pressure containers, large oil reservoirs, pressure pipes, etc. to be processed.
2. agricultural steel building is heat resistant and non-fire resistant
If the temperature is below 150oC, the properties of the steel change slightly. The steel structure is therefore suitable for hot workshops, but if the surface is exposed to heat radiation of approximately 150, it should be protected by a thermal insulation plate. If the temperature is between 300-C and 400-C, the strength and elasticity module of the steel material decreases significantly, and if the temperature is approximately 600-oC, the strength of the steel material is zero. In buildings with special fire protection requirements, the steel structure must be protected by refractory materials to improve fire resistance.
3. agricultural steel building has poor corrosion resistance
Especially in the vicinity of moist and corrosive media, it rust easily. In general, steel structures must be rusted, galvanized or painted and regularly maintained. Specific measures such as zinc-blockanode protection are required for offshore platform construction in seawater to protect corrosion.
4.The demolition of agricultural steelworks is not subject to any building protection and the steel can be recycled and reused.
The grid structure of the agricultural steel building has an adequate load, a high stiffness, a low weight, individual rods and a comfortable production and installation. In recent years, it has often been used in public and industrial buildings with large stretches and large columns. In the construction of agricultural steel buildings there are stainless steel sandwich plates, profile plates, lighting materials and other roof materials. It can be used not only for roof constructions, but also for floors, walls and special constructions.
Agricultural steel production plays an essential role in the current industrial production process. Qingdao Xinguangzheng Steel Structure Co., Ltd. has undertaken to offer the most suitable agricultural steel buildings at a reasonable price.
Prefab house is a structure mainly made of steel, which is one of the main building structure types. The characteristics of steel are high strength, light weight, and high rigidity, so it is especially suitable for the construction of large-span, super-high and super-heavy buildings.
Compared with traditional concrete buildings, what are the advantages of Prefab house?
What are the advantages of Prefab house?
What is the installation process of Prefab house?
Compared with prefabricated concrete buildings, Prefab houses have the following advantages:
1. There is no on-site cast-in-place node, the installation speed is faster, and the construction quality is easier to be guaranteed;
2. The steel structure is a ductile material with better seismic performance;
3. Compared with concrete structure, steel structure has lighter weight and lower foundation cost;
4. The steel structure is a recyclable material, which is more green and environmentally friendly;
5. Well-designed steel structure prefabricated buildings are more economical than prefabricated concrete buildings.
6. The cross-section of beams and columns is smaller, and more usable area can be obtained.
Save heating costs
Prefab house is more energy-efficient and environmentally friendly when used in the home, such as a new type of thermal insulation layer that has a better thermal insulation effect. When a household measurement is implemented and the heating has the same temperature, the room temperature of the "assembled" space is higher. The head of household may consider lowering the heating temperature, saving heating costs and, at the same time, reducing energy consumption.
Save energy
Finished house is of great benefit for energy saving and environmental protection. Through factory production and on-site assembly, it can significantly reduce building protection and waste water, reduce building noise, reduce harmful gas and dust emissions and reduce building and management personnel on site.
The assembly procedure for the steel construction of the Prefab house: steel column assembly -Installation of the supports between the columns -temporary installation of the steel bearer -roof bearings, roof bearings -correction and fixing of the steel bearer -Installation of the maintenance structure.
1. Contamination protection: Avoid rain water entering the metal roof from the outside. Rainwater enters the metal roof mainly through overlapping joints or knots. In order to achieve the function of the centrifuge, it is necessary to use a sealing disc at the screw connection and to make a concealed fixation. Use sealants or welds on the top of the plate. Best use a long board to remove the overlap. Close water-tight treatment for bleeding.
2. Moisture resistant: Avoid condensation of water vapour in the soil and metal wax layer and drain the water vapour in the metal wax layer. The solution is to fill the metal roof with thermal insulation cotton, place a waterproof membrane on the metal floor plate and have ventilated knots on the metal roof.
3. Daylight: Improve indoor lighting during the day by means of skylights and save energy. When installing daylight panels or daylight glass at certain points on the metal roof, the duration of use of the daylight should be aligned with the metal ceiling panel and the connection between the daylight and the metal ceiling panel should be treated watertight.
Seeing this, do you also want to order an Prefab House? If necessary, you can contact Qingdao Xinguangzheng Steel Structure Co., Ltd. they will provide the Prefab House of the best quality.