











Agricultural steel building has low cost, short construction time, and less pollution. Therefore, it has become the best choice for new-style construction.
Structural parts: material, surface roughness, tolerance, surface treatment, straightness (or radian)
Connection: hole position deviation, bolt grade; welding method, welding standard, welding material; air tightness, non-destructive testing, liquid penetration testing, etc. are required
Overall structure: verticality, horizontality, etc.
Packaging: packaging materials, packaging methods
Storage: ambient temperature, ambient humidity
Transportation: loading and unloading, placing in vehicles, placing in containers, etc.
Fire protection technology. One of the most critical issues in agricultural steel building is the application of fire protection technology. The fire resistance rating of light steel structure houses is level 4. For light steel structure residential buildings, fire-resistant gypsum boards are pasted on both sides of the wall and the ceiling of the floor. For ordinary firewalls and household walls, 25.4 mm thick (1 inch) gypsum boards are used to protect them to meet the 1-hour fire protection requirement. The glass fiber filled between the wall columns and the floor joists also plays an active role in protecting fire and heat transfer.
Sound insulation technology. The agricultural steel building is filled with glass wool between the inner and outer walls and the floor joists, which effectively prevents the audio part transmitted through the air. For the impact sound transmitted through the solid, the following construction is performed: the partition wall is composed of two wall columns. There are two walls with intermediate spaces; for the small keel used to fix the gypsum board for the suspended ceiling, an elastic structure with small cut grooves is used to effectively reduce the transmission of structure-borne sound between floors.
If an agricultural steel building is damaged, we must immediately recognise and remedy the problem. The main factors of steel structural damage are:
(1) the structural viability of agricultural steel buildings is insufficient due to changes in load, overdue service and changes in rules and regulations;
2) The components of agricultural steelworks are deformed, twisted, damaged, deformed, etc., due to various accidents; which results in a weakening of the cross-section of the component, a twisting of the rod and a tearing of the connection;
(3) deformation, cracking and retardation of agricultural steel components or connections due to temperature differences;
4) The agricultural steel structure corrodes due to the erosion of chemical substances and electrochemical corrosion leads to a weakening of the cross-section of the steel structure;
5) Other include errors in design, production, construction and illegal use and operation during the service period.
There are three main technical reinforcement measures for agricultural steel construction:
1) Cross-section defences: Apply the element locally or over the entire length of the element with steel and connect it to a whole to carry the force together;
2) Change the calculation diagram: add additional supports, adjust load distribution, reduce cutting force level, force displacement of static indefinite structural support and reduce peak voltage;
3) Pre-tensioned cable method: use high-strength cables to strengthen the weak links of the structure or to improve the overall durability, stiffness and stability of the structure.
Qingdao Xinguangzheng Steel Structure Co., Ltd. has been developing agricultural steel buildings for many years, and is known as "the national brand leader in the Chinesesteel building industry". Therefore, customers can choose their products with confidence.
A lot of work is needed to promote and improve the design specifications and construction technical standards of different types of structures, and to develop new types of lightweight insulation wall materials and the supporting issues of residential components. At the same time, it is necessary to widely publicize the advantages of the development of Residential steel building, so that more developers, designers and users can understand and understand steel structure housing.
What are the main forms of Residential steel building?
What are the structural characteristics of these Residential steel buildings?
What should I pay attention to when using Residential steel building?
Judging from the Residential steel building that has been built, the king has:
1) Thin-walled steel composite wall panel form;
2) Pure frame form;
3) Frame support form;
4) Form of steel-concrete combination;
5) Steel frame-concrete seismic wall form and so on.
The structural forms of Residential steel building have their own characteristics. Among them, the thin-walled steel composite wall panel is particularly suitable for finalized products. The Residential steel building system evolved from the wall panel structure, that is, the thin-walled steel column members are arranged at a distance of about 600mm. The vertical load-bearing structure and section steel have a support system to resist horizontal forces. The floor slab is arranged as a multi-rib support structure according to the position of the vertical section steel. Because the upper structure is a wall-like structure, the foundation is set as a strip foundation according to the force. The foundation requirements are not high.
The thin-walled steel composite wallboard residence is affected by the dense structure, and there are certain restrictions on the size of the partitions, door, door and window openings, and pick-out components.
The latter several forms of Residential steel building can meet the design requirements of multi-story residential buildings, but there is a common problem from the perspective of use, that is, the impact of the prominent beams and columns on the interior look and feel of the residence.
Compared with other buildings, Residential steel building has its particularity. Offices and workshops can use a relatively fixed column network, and the storey height is also higher. The space occupied by the beams and columns is suitable for people. The rules of the column network are conducive to the beams. Layout. On the contrary, the residence is a product with many changes. According to the requirements of the building, a regular column network is rarely arranged. The interior space of the house is relatively small and changes a lot, which is not conducive to the layout of the steel frame.
After seeing this and learning so much information about residential steel structures, I believe you must also want to order a Residential steel building. Qingdao Xinguangzheng Steel Structure Co., Ltd. can provide the best Residential steel building you need. At the same time, their after-sales service is also very considerate.
Prefab house is a structure mainly made of steel, which is one of the main building structure types. The characteristics of steel are high strength, light weight, and high rigidity, so it is especially suitable for the construction of large-span, super-high and super-heavy buildings.
Compared with traditional concrete buildings, what are the advantages of Prefab house?
What are the advantages of Prefab house?
What is the installation process of Prefab house?
Compared with prefabricated concrete buildings, Prefab houses have the following advantages:
1. There is no on-site cast-in-place node, the installation speed is faster, and the construction quality is easier to be guaranteed;
2. The steel structure is a ductile material with better seismic performance;
3. Compared with concrete structure, steel structure has lighter weight and lower foundation cost;
4. The steel structure is a recyclable material, which is more green and environmentally friendly;
5. Well-designed steel structure prefabricated buildings are more economical than prefabricated concrete buildings.
6. The cross-section of beams and columns is smaller, and more usable area can be obtained.
Save heating costs
Prefab house is more energy-efficient and environmentally friendly when used in the home, such as a new type of thermal insulation layer that has a better thermal insulation effect. When a household measurement is implemented and the heating has the same temperature, the room temperature of the "assembled" space is higher. The head of household may consider lowering the heating temperature, saving heating costs and, at the same time, reducing energy consumption.
Save energy
Finished house is of great benefit for energy saving and environmental protection. Through factory production and on-site assembly, it can significantly reduce building protection and waste water, reduce building noise, reduce harmful gas and dust emissions and reduce building and management personnel on site.
The assembly procedure for the steel construction of the Prefab house: steel column assembly -Installation of the supports between the columns -temporary installation of the steel bearer -roof bearings, roof bearings -correction and fixing of the steel bearer -Installation of the maintenance structure.
1. Contamination protection: Avoid rain water entering the metal roof from the outside. Rainwater enters the metal roof mainly through overlapping joints or knots. In order to achieve the function of the centrifuge, it is necessary to use a sealing disc at the screw connection and to make a concealed fixation. Use sealants or welds on the top of the plate. Best use a long board to remove the overlap. Close water-tight treatment for bleeding.
2. Moisture resistant: Avoid condensation of water vapour in the soil and metal wax layer and drain the water vapour in the metal wax layer. The solution is to fill the metal roof with thermal insulation cotton, place a waterproof membrane on the metal floor plate and have ventilated knots on the metal roof.
3. Daylight: Improve indoor lighting during the day by means of skylights and save energy. When installing daylight panels or daylight glass at certain points on the metal roof, the duration of use of the daylight should be aligned with the metal ceiling panel and the connection between the daylight and the metal ceiling panel should be treated watertight.
Seeing this, do you also want to order an Prefab House? If necessary, you can contact Qingdao Xinguangzheng Steel Structure Co., Ltd. they will provide the Prefab House of the best quality.
Ⅰ. Steel column installation for steel structure construction
1. Installation sequence of steel column:
① Foundation setting out → ② binding → ③ hoisting → ④ correction → ⑤ final fixation
2. Installation method of steel column:
(1) Setting out:
A. Elevation control:
In this structural steel construction project, iron parts and "middle bars" are controlled according to the depth of concrete cup mouth, the elevation of steel column bottom and the embedded elevation in the center of the bottom of the cup mouth during the construction of concrete foundation (φ30 steel bars), the elevation of top surface of "middle reinforcement" is based on the elevation of steel column bottom, and the elevation error of iron parts is controlled in ± Within 1mm.
To ensure the steel column is embedded in the foundation accurately and firmly φ On the 30 "middle reinforcement", weld a steel plate with thickness of 20 at the bottom of H-shaped steel column, as shown in the figure below.
When installing structural steel column, clean the foundation cup mouth first, and check the embedded elevation control "middle reinforcement" in the foundation(φ The actual height of 30 steel bars) is not necessary because the elevation embedded in the foundation construction has been controlled precisely, and no additional iron pad is needed. The method is simple, fast and efficient for the treatment of steel column feet. The construction is fast and the force is reasonable. When the column is lifted, it can be adjusted freely in several directions when the elevation is unchanged.
B. Before installation, the vertical and horizontal axis reference lines of the foundation plane shall be placed on the top of the cup mouth by woodworking ink bucket as the installation and positioning line of steel column.
(2) Column binding and hoisting:
A. after the steel column enters the site, the steel column shall be arranged according to the position of the lifting plan, and the model and number shall be checked to see if they are correct. The plane position of steel column after entering the site is shown in the following figure.
B. Before the column is lifted, a horizontal line shall be drawn with red oil paint 2300mm upward from the bottom of the column, so as to recheck the plane elevation datum before and after the installation and fixation.
C. the column installation belongs to vertical hoisting. In order to keep the suspended column drooping and facilitate the positioning, the binding point is determined at the lower part of the bracket. In order to prevent the sharp edges and corners of the column edge from damaging the lifting rope during hoisting, the rubber belt of the old car is used to separate and cover the edge and corner lifting rope. Pay attention to binding firmly and easy to remove.
D. temporary steel ladder and high-strength bolt installation fixture of working platform shall be bound on the steel column.
E. in order to avoid the free swing of the suspended column, hemp rope should be used to tie the upper part of the column bottom as a restraint rope and adjust the direction.
F. according to the site conditions, the rotation method is adopted for hoisting
After the preparations before hoisting are ready, the trial hoisting shall be carried out first. When the height of the steel column is 200 mm above the ground, the hoisting shall be stopped to check whether the rigging is firm and whether the crane is stable. After confirming that there is no problem, the crane can be directed to slowly lift, rotate to the top of the cup mouth, and then slowly descend. When the distance between the bottom of the column and the design position is 40-100 mm, adjust the two datum lines of the column body and the foundation to reach the accurate position, direct the crane to descend to the position, and temporarily fix the column with steel wedge (or wood wedge) and wind rope to remove the hook.
• Key points of rotation method:
The method of lifting the column by rotating the column around the column base is called rotation method, as shown in figure a below. When the column is hoisted by rotation method, in order to improve the hoisting efficiency, when the steel column enters the site, the binding point of the column, the center of the column base and the center of the cup foundation should be placed on the arc with the crane stop point as the center and the distance from the stop point to the binding point (i.e. the turning radius of the column), as shown in Figure B below.
The steel column hoisting is shown in the figure below:
(3) Preliminary correction of column:
The column should be corrected on the side with large deviation first, and then on the side with small deviation.
A. The correction of column generally includes plane position, elevation and perpendicularity.
B. When the steel column is hoisted in place, it is one-time alignment, and generally it does not need plane re correction. For the elevation of the column, it has been used before hoisting φ The embedded "middle reinforcement" can accurately control the elevation. Generally, it only needs to be checked, and it does not need to be corrected. Therefore, the steel column correction is mainly to correct the verticality and recheck the elevation.
C. In this project, the perpendicularity of the column is observed, and two theodolites are used for measurement and correction.
• First, place the theodolite on one side of the column, align the longitudinal center wire with the baseline of the column base, and then fix the screws of the horizontal plate.
• Measure the center line of the column and observe from bottom to top. If the vertical center line is aligned, that is, the column is vertical. If it is not aligned, the column shall be adjusted until it is aligned with the longitudinal center line of theodolite.
• Measure the horizontal line in the same way so that the center line of the other side of the column is perpendicular to the horizontal axis of the baseline. After the column is accurately positioned, the column can be fixed.
• Verticality correction of steel column: distance adjusting screw rod and steel wedge are used. Due to the small contact surface of the long side of the column, the base plate is set during the construction. The details are as follows.
The manufacturing dimension of steel wedge is shown in the figure below:
(4) Final alignment and fixation of steel columns:
After the steel column is hoisted in place, the column correction mainly involves the adjustment of elevation and the correction of verticality; The correction method can use tools such as wind rope, Jack, crowbar and steel wedge (or wooden wedge) to apply vertical force and lateral force of pulling, jacking, supporting and prying to the steel column.
Adjust the verticality, positioning axis and elevation of the column. After confirming the correctness, the gap between the steel column and the foundation cup mouth shall be poured with C40 fine stone concrete. The expansive high strength grouting material is preferred.
Ⅱ Protection of site components:
1) The unloading of components shall be careful to prevent damage and prevent collision and extrusion between members.
2) The members shall be stacked in order at the designated site, and the number of layers stacked by steel beams shall not exceed 3 layers to prevent the members from squeezing and deformation.
3) Before hoisting, oil, sediment and dust on the surface of the components shall be cleaned.
Ⅲ The placement of components and the requirements for the site
1) When unloading, the components are unloaded directly near the installation position and within the radius of rotation of the crane. Mark the number clearly with a clear color pen to facilitate lifting.
2) The components are placed in order in the site, and a certain gap is reserved between adjacent components to facilitate binding.
3) The site shall be solid and flat, and the components shall not be polluted due to rain and snow, and the vehicle with 30 ton level can be walked.
Ⅳ Steel structure building installation
Preparation before hoisting of steel column:
Before hoisting the steel column, the cable wind rope shall be tied to the column body. The lifting point shall be at the bracket position, and the double wire rope shall be set up and down, and the snap ring can be checked to be qualified before entering the next work. Before hoisting the steel column, the positioning axis, foundation axis and elevation, cup opening size and the height of the bottom standard of the steel column must be inspected and handed over and accepted. The number, outline dimension, screw hole position and diameter of the steel column shall be comprehensively reviewed. After confirming that it meets the requirements of design drawings, draw out the installation center line and the lower end elevation line of the steel column.
Ⅴ Steel column hoisting
(1) installation method of steel column
Before lifting the steel column, the wooden board shall be fixed at the column foot to prevent damage to the column foot and other structures.
Special hoisting steel wire rope is used for steel column binding. Wood or rubber sheet shall be used to prevent damage to the steel column.
The steel column is installed by a 25t truck crane. When the steel column is lifted, the crane shall hook and rotate the arm while lifting the steel column to make the steel column vertical away from the ground.
(2) positioning adjustment and temporary fixation
When the steel column is lifted to 200mm above the base cup mouth, it will be stable, and it will fall slowly at the base cup mouth. Avoid hitting the concrete edge of the foundation cup mouth during falling. After implementation, use special angle ruler to check, adjust the steel column to make its positioning line coincide with the foundation positioning axis. Three people are required to operate the adjustment, one person moves the steel column, one person helps to stabilize and the other person conducts the test. The positioning error is controlled within 2mm.
(3) when adjusting the elevation of the steel column, place the pad iron at the bottom of the cup foundation, use the level to super level the bottom plate elevation of the steel column as the top elevation of the pad iron, so that the elevation after the steel column is in place can meet the design elevation requirements, mark the elevation datum point on the column body, and then use the level to measure the installation elevation after it is installed in place.
(4) the verticality of the steel column shall be preliminary adjusted by the level ruler. Then two theodolites are used to observe from both sides of the column at the same time, and the adjustment is carried out by relying on the cable wind rope. As shown in the figure below:
Diagram of verticality adjustment of steel column
(5) after the adjustment, use eight iron wedges to position the gap between the bottom of the steel column and the base of the cup mouth, and then spot weld the column to make it stable.
Ⅵ Steel beam installation
Steel beams must be stacked in order on site for this steel work in construction. Sleepers must be placed in the middle of each layer of steel beams. Two lifting points for steel beam hoisting are selected on both sides of the center of gravity of the steel beam. The two lifting points should be 800mm away from the support and the middle of the span, and the distance between the two lifting points should be increased according to the length of the steel beam.
To ensure safety and prevent the sharp edge of the steel beam from cutting the steel wire rope, the steel wire rope shall be protected, the angle of the sling shall not be less than 450, and the steel beam shall be directly tied and rolled with the steel wire rope or lifted with a special fixture.
Before hoisting the steel beam, install the safety rope on the steel beam. When hoisting, hang two sliding ropes at both ends of the steel beam. Two people pull two sliding ropes respectively. The hoisting speed of the steel beam must be slow. In order to ensure safety, personnel should not stand directly under the beam. The cloth bags specially used for placing high-strength bolts are put on both ends of the steel beam. When the steel beam is hoisted above the position, the steel beam is put in place. The falling speed of the steel beam is controlled at 3m / min. two installers are arranged at both ends of the steel column head to prepare for the installation of the steel beam. When the steel beam is close to the in place position, two installers should hold the upper flange of the steel beam with their hands respectively, drag the steel beam to the in place position, and prepare to install the high-strength bolts.
Ⅶ Installation of retaining structure and support corner brace
1) Installation of roof purlin: when the main structural steel forms a frame section, the roof purlin is hoisted to the main beam of the roof with a crane and installed manually. The purlin can also be manually pulled onto the roof with a white synthetic rope for installation. After the installation of purlin, the purlin support is installed in time.
2) Wall purlin installation: when the main structure forms a frame section, the construction personnel stand on the scaffold platform and pull the wall purlin to the installation position with white comprehensive rope.
3) Corner brace installation: after the main body is welded, the corner brace is connected.
Ⅷ Measurement and correction of steel column
Verticality correction of steel column
When the steel column is installed and corrected, two theodolites are set up on the control line with 90 degree translation of 1 meter each other, and the theodolite operators observe the small steel ruler on the top of the column, measure the deviation of the steel column and direct the correction.
A. Control the verticality of the steel column between the first hoisting joints.
B. Steel column calibration is divided into four steps:
initial calibration during initial tightening; Re-calibration before final tightening; Tracking and monitoring during welding process; Final result measurement after welding.
The perpendicularity can be roughly controlled with a long level before the initial tightening, and it can be accurately corrected after the frame is formed. After welding, retest shall be carried out, and the measurement results shall be compared with those at final tightening, so as to be the basis for the next construction.
C. Verticality measurement method of C steel column
Initial correction: the perpendicularity of the steel column is preliminary adjusted with a level ruler.
Accurate correction of steel column perpendicularity: one column grid is used as an installation section for the hoisting of the main frame until the hoisting of three continuous complete sections is completed
After the whole is formed, the measurement correction can be inserted. Two theodolites are used to observe from both sides of the column at the same time, and the wind rope is used for correction and adjustment.
Ⅸ Steel structure survey
2) Elevation control of steel column
Based on the elevation reference point of the plane layer where the steel column is located, the deviation value of the horizontal elevation of the steel column is measured with the level gauge and the correction is directed.
3) Steel beam measurement
After the steel column is hoisted and corrected, the +1.00m control point shall be measured to each steel column according to the site level as the basis for vertical transfer of elevation and the elevation of beam installation; Pop up the center line of the steel beam on the surface of the steel beam.
The control axis is measured to the column body to control the beam position offset; The accuracy of beam elevation is controlled according to the control point of column elevation. Set up theodolite on the floor platform, and then look at the cross angle to the axis of the corresponding beam. Aim at the center line of the upper surface of the beam to the other end with theodolite to see if the number coincides with the axis of the beam.
Calculation of survey and lofting data
In this project, the computer automatic query method is used to calculate the survey and lofting data. The specific steps are as follows:
1) The establishment of data model
Firstly, according to the design coordinates and the dimension relationship of each building in the design drawing, the building, building axis, control line to be lofted and so on are drawn in AutoCAD according to the proportion, and the data model is established.
2) Survey and lofting data query
After drawing the survey loft data model, the survey loft data such as the angle and distance between the known basis (axis control pile, lofted axis, etc.) and the control line to be lofted are queried by using the command of dist of AutoCAD.
3) Advantages of computer automatic query
The method of computer automatic query is used to obtain the required measurement and positioning data. It is not only convenient to calculate, but also has high precision. The distance precision can be set to 0.1mm, 0.01mm, and the angle precision to 0.0 ", 0.00" or higher according to the actual situation.
Ⅹ Construction of high strength bolt
1. Preparation before installation
1) Test and inspection of high strength bolt
Anti slip coefficient test
The project adopts class 10.9 large hexagon high-strength bolts. The anti slip coefficient test of high-strength bolts shall be conducted by taking the most representative thickness of the plate in the project for test, and three groups shall be made.
The size of the specimen plate is as follows:
Axial force test
Randomly select the bolts to be installed at the construction site, and 8 sets of bolt pairs are selected for re inspection in each batch.
2) Transportation and storage of high strength bolts
transport
The form, size and technical conditions of high-strength bolt connecting pair shall be manufactured and supplied by the manufacturer according to batch, with factory certificate and high-strength bolt connection pair, which shall conform to the provisions of national standards gb1228-1231-84 and gb3632-3633-83. High strength bolts with large hexagon for steel structure
The connecting pair consists of a bolt, a nut and two washers. The combination of use shall meet the national standards, and the high-strength bolt connection pair shall be supplied with storage and transportation in the same batch.
The high-strength bolt connecting pair shall be installed and placed lightly during loading, unloading, transportation and storage to prevent the packing box from being damaged or damaged.
Storage of high strength bolt warehouse
1. the high-strength bolt connection pair shall be cleaned according to the specification, batch number and supply date of the packing box, and shall be kept in the indoor warehouse, and the accumulation shall not be higher than 3 layers. The indoor moisture-proof, long-term dry, rust and dirt contamination shall be prevented, and torque coefficient shall be prevented from changing. The bottom layer shall be more than 300mm above the ground level.
2. when installing on site, the quantity of high-strength bolts required on the day shall be issued. The rest should be kept properly. Do not put it in disorder, damage the thread, and be contaminated with dirt.
3. before using the long-term storage high-strength bolt connection pair, a comprehensive quality inspection shall be conducted again. If any abnormal phenomenon is found after unpacking, the inspection standard shall be conducted according to the relevant provisions of national standards gb1228-1231-84 and gb3632-3633-83. It can be used after being qualified.
3) Construction management of high strength bolts
1. Construction Manager
When carrying out the construction of this high-strength bolt, the high-strength bolt manager shall be determined first to be responsible for the project management, quality management and guidance of the construction personnel.
2. weather management (climate conditions)
In principle, no operation shall be carried out during rainfall and snowfall. If rain or snow fall occurs during operation, the speed shall be accelerated to lock the unfinished ones
3. friction surface management
Before tightening, the friction surface shall be inspected first. If there are any attachments to reduce bearing capacity of friction surface, such as rust, oil, paint and residue, metal brush, sandpaper and oxygen acetylene flame shall be used for removal.
4) Construction of high strength bolts
1. final tightening of temporary bolts
Before inserting high-strength bolts, temporary bolts shall be used to tighten the connection tightly, if the materials of the connection parts are bent or warped, they shall be corrected.
If the difference of holes is within 2mm, it can be corrected by cutter.
If the difference of holes exceeds 2mm, reasonable treatment methods such as replacement of panel shall be adopted based on consultation with management personnel, and gas cutting and reaming are not allowed.
2. high strength bolt insertion
The nut and gasket of high-strength bolt shall pay attention to the installation direction, and install according to the following figure.
When inserting bolts, pay attention not to attach rust, dust, oil, etc. to the bolts. In addition, do not force into the bolt hole during construction to avoid damaging the thread.
3. initial tightening
After the temporary fixing bolts are locked, confirm the compactness of the components.
After initial tightening, mark with white marker through bolt nut, gasket and component.
When using the inspection wrench, although the torque value can be confirmed by the contact sound, it is easy to over tighten if the mechanism continues to apply force, so it should be noted.
4) Final tightening
After initial tightening, use special fastening wrench to lock until the neck is broken.
In principle, the bolts inserted on the same day shall be screwed out on the same day.
The beam-column joints of Prefab House are mainly connected by bolt welding. However, bolted joints are recommended for fabricated steel structures. The advantage of bolted connection (weld-free connection) is that the installation speed is fast and the construction quality is easier to control.
1. The construction period is short. Generally, the first floor of Prefab House can be built in three or four days, and it only takes one or two days. Steel structure residential systems are mostly manufactured in factories and installed on-site. The amount of on-site work is greatly reduced. Therefore, the construction period can be greatly shortened, and the noise and dust generated during the construction, as well as the consumption of on-site resources and various on-site expenses are correspondingly reduced. Compared with reinforced concrete structures, the construction period can generally be shortened by one-half, the investment benefits can be brought into play in advance, capital turnover can be accelerated, and construction costs can be reduced by 3%-5%.
2. Good seismic performance. Because the steel of Prefab House is an elastically deformable material, it can greatly improve the safety and reliability of the house. The steel structure has high strength, good ductility and light weight, which can greatly improve the mechanical performance of the structure, especially the seismic performance. Judging from the situation after the earthquake at home and abroad, the number of collapsed steel structure residential buildings is very small.
In line with the development direction of building energy efficiency. Prefab House uses steel as the frame and thermal insulation wallboard as the enclosure structure, which can replace clay bricks, reduce the amount of cement, sand, stone, and lime, and reduce the damage to non-renewable resources. On-site wet construction is reduced, and the construction environment is better. At the same time, steel can be recycled and reused, and the environmental pollution during construction and dismantling is small, and its energy saving index can reach more than 50%, which belongs to the green building system.
The application of steel structure in Prefab House has opened up a new application market for my country's steel industry. It can also drive the research and application of related new building materials.
Steel-finished house is generally a residential building constructed with factory-made, economical steel profiles as a supporting work and new lightweight, heat-conserving, heat-insulating and high-strength wall materials as a home. The industrialisation of the steel building house refers to the use of steel construction houses as the final product. Through socialized mass production, the process of investment, development, construction, construction and customer service of steel dwellings is centralised and unified into an overall organisational form. The industrialization of the steel building house is the development trend of the steel building house.
Knowing this, do you also need to order a Prefab House? Qingdao Xinguangzheng Steel Structure Co., Ltd. is committed to providing various Prefab Houses with high quality for all customers from all over the world.
Industrial steel building mainly refers to that the main load-bearing components are composed of steel. Including steel column, steel beam, steel structure foundation, steel roof truss (of course, the span of the plant is relatively large, and they are basically steel structure roof truss now), steel roof. Note that the wall of steel structure can also be maintained by brick wall.
What should be taken into account in the day-to-day maintenance of industrial steel buildings?
What are the arrangements for the planning of industrial steel buildings?
What should be taken into account when selecting industrial steel building?
After the installation of our industrial steel building, the owner is not allowed to change its structure privately, not to remove screws and other parts, and not to increase or reduce the partition wall. If you need to change a part, you need to negotiate with the manufacturer. It is up to the manufacturer to decide whether it can be changed. After approximately three years of use, the steel structure must be maintained with colour to give the building beauty and safety. industrial steel buildings are connected by steel construction components, so electrical devices such as wires should be insulated by cable channels in order to avoid accidents involving electric shocks.
The maintenance of industrial steel buildings is closely linked to the durability of the steel structure. That is why the industry pays enough attention to it. If you have problems with maintenance and maintenance, you should contact a professional steel construction manufacturer for help.
1. Insurance: Avoid rain water from the outside entering the metal roof of the industrial steel building. Rainwater enters the metal roof mainly through overlapping joints or knots. In order to achieve the function of the centrifuge, it is necessary to use a sealing disc at the screw connection and to make a concealed fixation. Use sealants or welds on the top of the plate. Best use a long board to remove the overlap. Close water-tight treatment for bleeding.
2. Fire protection: The metal material does not burn in the event of fire and the flame does not penetrate the metal roof plate.
3. Wind pressure resistance: industrial steel building can withstand the maximum local wind pressure and the metal roof plate is not removed by negative wind pressure. The wind resistance depends on the strength of the metal roof plate and the fixing seat and the density of the fixing seat.
Sound protection: industrial steel building prevents sound transmission from the outside to the inside or from the inside to the outside. Fill the metal sheet with sound insulation material (mostly insulated cotton) and the sound insulation effect is expressed by the sound intensity difference on both sides of the metal sheet. The sound insulation effect depends on the density and thickness of the sound insulating agent. Note that sound insulating agents have different locking effects on sounds of different frequencies.
After reading these words, do you also want to order an industrial steel building? If necessary, you can contact Qingdao Xinguangzheng Steel Structure Co., Ltd., which is an advanced industrial steel manufacturer.
At present, the construction technology of large-space steel structure construction has made great progress, and the "folding and unfolding" construction technology is a construction method that fully expresses the changes in the construction process of large-span space construction. He turned a large structure into a movable mechanism; the industrial steel building is so popular nowadays mainly because its advantages surpass the previous buildings.
What is the meaning of industrial steel building?
What should I pay attention to when installing steel columns in industrial steel building?
What should be paid attention to when constructing industrial steel building?
The use of steel construction in industrial steel building has the advantages of shorter construction period, higher application rate, sensitive plan, column spacing and large span. As far as the owner is concerned, industrial steel building can shorten the investment construction period and work quickly. The components can be disassembled and re-applied, which promotes environmental protection and saves resources. Therefore, the application in modern industrial design is becoming more and more common.
(1) Due to the heavy weight and long length of the steel column, the industrial steel building cannot be manufactured and transported at one time. Therefore, the method of segmented manufacturing and on-site assembly as a whole is used for hoisting. It is planned to divide the steel column into two sections. The steel column is transported to the site in two sections, the lower lattice part and the upper H-shaped steel column. The weight of the steel column is about 6 tons, and the height in place is about 17 meters. A 50-ton truck crane can meet the hoisting needs, supplemented by a 25-ton truck crane for hoisting.
(2) The hoisting adopts single-machine rotary hoisting. Before lifting, padded wooden squares at the position of the steel column foot plate to prevent the steel column from damaging the foot plate during the lifting process. When the steel column is hoisted, the crane should lift the hook while turning the arm to make the steel column vertically off the ground and put the column into the mouth of the cup.
Ventilation: air exchange in indoor and outdoor areas. Put air vents on the metal roof.
Moisture resistant: Avoid condensation of water vapour in the lower layer of the metal roof and metal roof layer and drain the water vapour in the metal ceiling layer. The solution is to fill the metal roof with thermal insulation cotton, place a waterproof membrane on the metal floor plate and have ventilated knots on the metal roof.
Carrying: construction load, rain, dust, snow pressure, maintenance load. The load bearing capacity of the metal roof depends on the cross-section characteristics of the plate type, the strength and thickness of the material, the power transfer method and the distance of the horses (sub-horses).
Lightning protection: Take the lightning to the ground to prevent the lightning from penetrating the metal roof and entering the room.
After reading this, do you have a better understanding of industrial steel building?? If you want to know more about related products, you can come to the website of Qingdao Xinguangzheng Steel Structure Co., Ltd., they will provide the most considerate service and the highest quality industrial steel building?.
Production introduction
Project Name: Sri Lanka Steel Structure Senior Resort Hotel
Project area: 110 square meter per unit
Project location: Sri lanka
Project Overview: As a second floor Resort, wall panel is cement sandwich panel as insulation, and the surface is painting with real stone paint. The roof is UPVC composite tile. Iron fences and stairs also is our company product.