Generally speaking, the installation procedures of industrial steel building include installation of steel columns, installation of inter-column supports, temporary installation of steel crane beams, roof beams, roof supports, steel crane beams, etc., correction, fixation, and structural installation of maintenance.
What is the specific process of industrial steel building construction?
How to regularly maintain industrial steel building?
How to consider the cost of industrial steel building construction?
1. Lifting the main structure of industrial steel buildings: connecting steel carriers on the ground, erecting steel columns, lifting steel carriers, connecting secondary structures, correcting the deviation of the main structure, installing crane carriers (optional), lifting intermediate layers (optional), and coating with fire resistant paint pack.
Main control quality: The deviation of the main structure should meet the specifications and design requirements and the initial and final application of high-strength screws should meet the requirements.
2. Installation of secondary structure: roofing posts, roof wall supports, flange supports, etc.
3. Laying of roof plate and insulation layer: first lay insulation layer, then assemble roof plate (in some projects a position of steel fabric is also placed under the insulation layer to prevent a fall of the insulation layer, this mainly depends on insulation layer level)
Main quality control: The roof is mainly waterproof, therefore the plate should be covered with the plate, the nail position, the glue coating should be full or not, the glue should be wiped clean and the coating on the surface of the plate should not be damaged to rust etc. to avoid.
industrial steel building wall maintenance and installation: mainly the installation of wall insulation and wall panels.
The main quality control of industrial steel building: the wall is mainly an aesthetic problem, and a window area is waterproof. There is also the problem of installation deviation. For example, the bottom should be flat, the entire plane should be flat, the flatness deviation between the board and the board should meet the requirements, and so on.
The detailed structure of the industrial steel building: mainly the installation of some trims, such as the wrap angle between the roof and the wall, the wrap angle at the corner of the wall, the flooding board between the wall panel and the brick wall, the door and window trim, etc.
The price of industrial steel building can only be compared with certain basic conditions, such as whether it is imported or domestic color panels, its thickness, coating; insulation material and thickness; whether there is a skylight; workshop bays and spans; whether there are cranes, crane tonnage, Many factors such as the level of the work system are related, and the impact of the price difference in other regions and the qualification level of the construction unit cannot be ignored.
The industrial steel building has achieved an irreplaceable position in industrial production. Qingdao Xinguangzheng Steel Structure Co., Ltd. is committed to providing different kinds industrial steel buildings of high quality for all customers from all over the world.
The development of residential steel building conforms to the industrial technology policy of protecting arable land and saving energy, and is also one of the production methods for realizing residential industrialization. The development of steel structure housing is the general trend.
What is the layout of the residential steel building?
What issues should be paid attention to when designing residential steel building?
Why pay attention to the design of residential steel building?
residential steel building’s column grid layout should be regular, and it is advisable to use residential units or sleeves as the unit to achieve modularity. The modular flat connection, wrong connection and symmetrical concave (convex) connection and other splicing adapt to changes in the overall layout .
When the residential steel building module adopts small column net, it should be combined with the floor and pipeline design; when the module adopts large column net, the facility pipeline should be designed as a fixed-positioned tube bundle, and the electrical and communication lines can be along the cavity and skirting of the partition wall. , Mirror hanging line or top line arrangement.
The kitchen and bathroom are located close to the concrete core tube or concrete shear wall, and avoid steel structure load-bearing components to facilitate the fire prevention and anti-corrosion treatment of steel components.
Vertical pipelines are centrally arranged in pipeline wells or pipeline walls, or installed on site using factory prefabricated tube bundles.
The toilet is drained on the same floor. Use a double pipe system for centralized heating, and use a temperature control valve and a heat meter. Use the equipotential characteristics of the steel structure to make a natural ground connection.
residential steel building should be dominated by construction and design, and other professions should interact closely with each other. In addition to following the general principles of residential building design, residential steel building must also focus on solving:
(1) How to make use of the advantages of steel structure? The beam span can be enlarged, the bays can be more flexible, and more space can be created for residents. But how to avoid the flatness and monotonous facade of the building caused by the steel structure.
(2) It is necessary to solve the fire protection and anti-corrosion problems of steel structure residential buildings. Especially in rainy areas, the quality of anti-corrosion and anti-rust work directly affects the promotion of steel structure housing.
The cost of residential steel building is the most concerned issue of real estate developers. Steel structure residences should be positioned in middle and high-end residences. Steel structure residences are a systematic project. Management and coordination should be strengthened from design, manufacturing, transportation, installation, maintenance and management, so as to reduce costs and improve overall economic benefits. the goal of.
Qingdao Xinguangzheng Steel Structure Co., Ltd. strives to provide top-quality residential steel buildings with reasonable prices, efficient production time, and the most professional customer service.
Introduction of Maldives Prefabricated Steel Structure Construction Mall Building Hardware Store:
Project Area: 3323 ㎡
Project Date: 2017
Project Detail: Six-story steel structures, 100mm fiberglass wool sandwich panel for roof and Glass Curtain +Aluminum Wall Cladding for outer wall and 75mm rock wall sandwich panel as inter wall. The fireproof grade is grade 2, and the fireproof coating is indoor thin fireproof coating.
Effect picture of Maldives Prefabricated Steel Structure Construction Mall Building Hardware Store :
Company information
Qingdao Xinguangzhegn steel structure group company has 1200 workers, 360000 ㎡ non-dust workshop, 25 years experience, CE, ISO9001, ISO9712, ISO3834, BV, SGS certificated, one hour reach Qingdao port, our company, as a manufacture, this is how we keep good quality and competitive prices for global valued customers.
We provide steel building design, farm house design, manufacture and installation service.
Prefab House refers to the use of industrial production methods to build houses, that is, the stairs, exterior walls, balconies, air-conditioning panels, etc. of the house are all prefabricated in the factory outside the construction site, and then shipped to the construction site for "assembly", and the interior of the house will be refined at one time. Handed over after renovation. That is, the huge external walls, stairs, and balconies from the factory are "assembled" on the construction site into houses and buildings.
What are the advantages of a Prefab House?
What are the structural types of Prefab Houses?
What should we be careful about when selecting a Prefab House?
1. Safe and reliable
The Prefab House with steel as the main building material has a high capacity per volume unit, is more stable and solid than the traditional brick and brick concrete technology, has a better seismic performance, wind resistance, water density and refractory performance and also has thermal insulation and sound protection functions. Steel has good ductility and can better use the energy brought in by earthquakes, so it has good seismic performance and a high structural security t hat guarantees the safety of stay.
2. Easy construction and short construction time
All components are prefabricated in the factory and only have to be installed on site, which greatly shortens the construction cycle. A 6000-square-metre-long building can basically be installed in 40 days.
1. Structural system
The structure of the Prefab House can be divided into: steel frame system, steel frame support system, steel frame-core tube system, steel frame-module-core tube system and steel frame-shear-wall system. With the continuous development of the technology, newer steel construction systems will also appear.
2. Peripheral protection system
The outer protective system of the Prefab House can be divided into blocks, plates, cans and other types.
3. Internal system
Traditional construction has many disadvantages. For example, the traditional rough decoration method does not separate the interior system and the structural system, which makes it difficult to adapt to the modern development of the housing industry; the house technology lines are not separated and the water and power lines are buried in the support layer, which the "century residence" cannot realize." The waste of social resources is serious.
1.The costs are relatively higher than in the traditional Prefab House made of brick concrete and concrete.
2. The steel structure of the Prefab House, with its unique steel structure, walls, roofs and other materials, as well as the standardized and final internal distribution and support facilities, is difficult to adapt to the habits of people "arbitrarily handling the house".
3. Corrosion of steel: Al-galvanized steel must be used for maximum corrosion protection and the main steel structure can reach fifty years.
4. There are many requirements for new materials. The structure of steel houses is equipped with materials such as thermal insulation and heat protection, usually using new lightweight materials.
Prefab Houses produced by Qingdao Xinguangzheng Steel Structure Co., Ltd. feature attractive appearance, excellent performance, user-friendly operation, easy maintenance, and internationally advanced performance indicators, and are exported to more than 10 countries and regions.
Project information
15 seconds to show you the speed of XGZ Prefabricated building
Total Building Area 3578.38 ㎡
200 Steel Columns
55 Integrated Floor Slab
Main Construction Completed in 15 days.
Description
Assembly new office building is a comprehensive project. Since the construction, through the development of detailed construction plan, it took only 4 months to complete the various links from the old Office demolition, civil construction, five floor platform assembly, curtain wall and maintenance plate installation, water supply and drainage circuit construction, elevator air conditioning installation and office building decoration, especially the five floor framework assembly link and decoration link which have exceeded the normal construction period On the basis of that, a breakthrough was made.
In the process of construction, all links are locked in close cooperation, construction and installation speed is fast, safety and quality are guaranteed, and a large number of assembly building installation technical details and practical experience have been accumulated.
Commercial steel building is a new type of energy-saving and environmentally-friendly building system. It is known as one of the "green buildings" in the 21st century. It is an energy-saving, environmentally-friendly, and recyclable building structure.
The general sequence of commercial steel building welding is: pre welding inspection → preheating and derusting → installation and welding of base plate and arc striking plate → welding → inspection
1. Before commercial steel building welding, check the groove angle, blunt edge, gap and staggered joint, and remove the rust, oil stain and iron oxide scale in and on both sides of the groove.
2. Preheating. Before commercial steel building welding, gas welding or special baking gun shall be used to heat the groove and the base metal within 100mm on both sides evenly, and the surface thermometer shall be used to measure the temperature to prevent the temperature from meeting the requirements or local oxidation on the surface and preheating temperature.
3. Recheck the preheating temperature. If the temperature is not enough, reheat it to make it meet the requirements.
4. When assembling and welding the backing plate and arc striking plate, the surface cleanliness shall be the same as that of the groove surface, the backing plate shall be close to the base metal, and the arc striking plate shall be firmly welded with the base metal.
1. Welding: the weld bead of the first layer shall seal the connection between the base metal and the backing plate in the groove, and then weld layer by layer until the groove is filled. After each weld is welded, the welding slag and spatter must be removed, and the welding defects shall be ground away and repaired in time.
2. An interface must be welded continuously. If it is necessary to stop welding halfway, it shall be subject to thermal insulation and slow cooling treatment, and shall be heated again according to the regulations before re welding.
3. In case of rain and snow, commercial steel building shall stop welding. There shall be a wind shield and canopy around and above the welded junction of components. When the wind speed is greater than 5m / s, the welding shall be stopped. When the ambient temperature is lower than zero, preheating and post heating measures shall be taken for construction according to regulations.
4. Carbon structural steel shall be subject to weld flaw detection after the weld is cooled to ambient temperature, and low alloy structural steel shall be subject to weld flaw detection 24 hours after completion.
5. Welders and inspectors of commercial steel building shall carefully fill in the operation record form.
When purchasing commercial steel building, we should pay attention to the design of waterproof, heat-insulating and anti-corrosion of the steel structure. The design documents did not specify the steel derusting grade and paint and coating thickness, and did not adopt corresponding measures according to the different fire resistance limits of different parts. commercial steel building of thermal insulation protection measures needs to be avoided.
Commercial steel building has focused on the development and production of commercial steel buildings for several years. And it commits to provide perfect service for every customer from all over the world.
Agricultural steel building components or parts are usually connected by welds, bolts or rivets. Because of its light weight and simple construction, it is widely used in various fields of agricultural production. Steel structure is easy to rust. Generally, steel structure needs to be derusted, galvanized or painted, and it needs to be maintained regularly. Here we are going to know more about the Agricultural steel building.
What are the architectural characteristics of Agricultural steel buildings?
What are the appearance characteristics of Agricultural steel building?
What should be paid attention to when constructing Agricultural steel building?
1. Industrialization of the production process. The steel structure is only connected by high-strength bolts. It also has the advantages of quick installation and return on investment.
2. Use high-quality materials with high toughness and plasticity. The quality is safe and reliable.
3. It also has the advantages of flexible design and decoration, low cost, and various colors.
The Agricultural steel building has no beams and no purlins, wide space, large spanning capacity, and the span of 6-32 meters can be chosen at will. Low cost, low investment, economical. The design and construction period is short,
The roof construction of Agricultural steel building can be completed in 20 days. Colored galvanized steel sheet, mechanical seam connection, natural waterproof, no leakage.
The Agricultural steel building is beautiful in appearance, sturdy and durable, and requires no maintenance.
The Agricultural steel building is light in weight, the overall structure is scientific and reasonable, and the wind and seismic performance is superior. Wind resistance and snow load, can withstand strong winds of 160km/n per hour, and can withstand a snow load of 148kg.
The shape of Agricultural steel building is beautiful, colorful, novel and full of rhythm. Rich and diverse roof forms give the building a new appearance.
The Agricultural steel building has complete functions, the roof slab and beam are integrated, and it integrates multiple functions such as heat preservation, heat insulation, ventilation, and lighting.
1 Personnel engaged in high-altitude operations must hold a certificate to work, and earnestly abide by the safety construction regulations, wear flexible clothing, and it is forbidden to wear hard-soled and slippery shoes with nails;
2 Workers of Agricultural steel building wear safety belts;
3 A safety net is set under the working surface of Agricultural steel building;
4 Materials for high-altitude operations should be stacked steadily. They should not be placed on the edge or attached to the opening of the hole. If there is a possibility of falling, they should be withdrawn or fixed in time to prevent falling objects from injuring people.
The Agricultural steel buildings made by Qingdao Xinguangzheng Steel Structure Co., Ltd. feature attractive appearance, excellent performance, easy maintenance, and internationally advanced performance indicators, and are exported to more than 10 countries and regions.
Agricultural steel building is a construction of steel materials and is one of the main types of construction. The structure consists mainly of steel bearings, steel columns, steel works and other components made of profile steel and steel plates and uses silanisation, pure manganese phosphation, washing and drying, galvanising and other rust and rust protection methods.
What is agricultural steel building?
What are the characteristics of people who opt for agricultural steel building?
What are the benefits of people opting for agricultural steel building?
The agricultural steel building is characterized by high strength, low weight, good overall stiffness and high deformation resistance. It is therefore particularly suitable for the construction of large-scale and ultra-high agricultural buildings; The material has a good homogeneity and isotrope, which is ideal for elasticity. The structure most closely corresponds to the basic assumptions of general technical mechanics; the material has good plasticity and toughness, can exhibit large deformations and can withstand dynamic loads well; construction time is short; the agricultural steel industry has a high degree of industrialisation and can be specialised in agricultural production.
1. agricultural steel building has good sealing performance
Since the welding design can be completely sealed, it can be air and water-tight to high pressure containers, large oil reservoirs, pressure pipes, etc. to be processed.
2. agricultural steel building is heat resistant and non-fire resistant
If the temperature is below 150oC, the properties of the steel change slightly. The steel structure is therefore suitable for hot workshops, but if the surface is exposed to heat radiation of approximately 150, it should be protected by a thermal insulation plate. If the temperature is between 300-C and 400-C, the strength and elasticity module of the steel material decreases significantly, and if the temperature is approximately 600-oC, the strength of the steel material is zero. In buildings with special fire protection requirements, the steel structure must be protected by refractory materials to improve fire resistance.
3. agricultural steel building has poor corrosion resistance
Especially in the vicinity of moist and corrosive media, it rust easily. In general, steel structures must be rusted, galvanized or painted and regularly maintained. Specific measures such as zinc-blockanode protection are required for offshore platform construction in seawater to protect corrosion.
4.The demolition of agricultural steelworks is not subject to any building protection and the steel can be recycled and reused.
The grid structure of the agricultural steel building has an adequate load, a high stiffness, a low weight, individual rods and a comfortable production and installation. In recent years, it has often been used in public and industrial buildings with large stretches and large columns. In the construction of agricultural steel buildings there are stainless steel sandwich plates, profile plates, lighting materials and other roof materials. It can be used not only for roof constructions, but also for floors, walls and special constructions.
Agricultural steel production plays an essential role in the current industrial production process. Qingdao Xinguangzheng Steel Structure Co., Ltd. has undertaken to offer the most suitable agricultural steel buildings at a reasonable price.